Supreme Court of India

RUDRADHAR R. TRIVEDI versus STATE OF MAHARASHTRA THROUGH THE SECRETARY AND ANR.

Decided
15 July 1996
Judges listed
K. RAMASWAMY (as the open data lists them; this may not name the whole bench)
Disposal
Dismissed

Citations

Official
[1996] SUPP. 3 S.C.R. 581 · 1996 INSC 739

Cited by

We found no other Supreme Court judgment we hold that cites this one.

Counted only in the Supreme Court judgments we hold whose text we could read, not in High Court judgments. We match each citation to a judgment automatically, so a citation we cannot match is not counted. "Cited" says only that a judgment refers to this one, not whether it followed, distinguished or overruled it.

The Court's text

Paragraphs from our copy of the Supreme Court Reports print, with the Court's own paragraph numbers, the printed page and, where printed, the margin letter. The Court did not number this judgment's paragraphs, so they are listed by page. Link to paragraph N with #para-N.

Unnumbered paragraph

We have heard learned counsel for the petitioner.

p. 582, margin A

Unnumbered paragraph

Notification under Section 4(1) of the Land Acquisition Act, 1894 (for short, the 'Act') was published on .July ll, 1953. Successive declaration under Section 6 came to be published in the year 1955-56. Thereafter, as many as 40 awards have been passed determining the compensation. In this case notice was issued by the second respondent on May 15, 1963 under Section 9 of the Act pursuant to which the petitioner had filed his objections. Thereafter, the award came to be made on 13.3.1985. He filed writ petition challenging the validity of the notification under Section 4(1) and the declaration under Section 6. Primary contention raised in the writ petition was that the petitioner had not been given notice under Section 5-A whereas being a sub-lessee, he was an interested person. The High Court was not impressed with the argument. He further contended that there was inordinate delay in passing thl! award. On that account, notification under Section 4(1) and declaration under Section 6 were required to be set aside. That contention was also negatived. The learned single .Judge by judgment dated February 16, 1996 dismissed the writ petition. On appeal, the Division Bench in the impugned order dated June 12, 1996 in Appeal No. 423/96 confirmed the same.

p. 582, margin B

Unnumbered paragraph

The learned counsel for the petitioner contended that since the land in an extent of 567 acres was acquired for public purpose, namely, establishment of IIT, transfer of 60 acres of lano to N!TIE by the UT by a resolution of the Government, viz., 95 of 1970, dated June 26, 1970 was clearly a fraud on public purpose. Therefore, the acquisition is not valid in law. In support thereof, the learned counsel placed reliance on the judgment of Bombay High Court in The Industrial Developn1e11t & lnvesl!nent Co. Pvt. Ltd. v. State of Maharashtra & 01"., AIR (1989) Born. 156 and of Delhi High Court in Union of India v. Nand Kishore, AIR (1982) Delhi 462. We find no force in the contention. It is settled law that the land acquired for public purpose can be transferred to another public purpose. Paramount consideration will be service of the public purpose. The NITIE is also one of the public institutions imparting technical education in the region. Under these circumstances, the transfer of 60.8312 acres of land handed over to NITIE pursuant to the resolution made by the Government is not vitiated by any error of law nor the notification under Section 4(1) and declaration published under Section 6 become bad in law. The aforesaid decisions bear no relevance.

pp. 582–583, margin E

Unnumbered paragraph

It is next contended that in view of the inordinate delay in passing the award, the acquisition should be required to be quashed. We find no force in the contention. It is seen that in Maharashtra State, as per the rules prevailing, pursuant to the notice under Section 5-A a personal hearing is required to he given to all the owners. In a massive acquisition like this, it would be well neigh impossible to the Land Acquisition Officer to pass the award within a short span of time. Under these circumstances, necessarily delay had occasioned in passing the awards. The petitioner had evoked at a belated stage in 1985, after practically 22 years. The High Court was, therefore, clearly right in refusing to exercise its discretionary jurisdiction under Article 226 of the Constitution.

p. 583, margin A

Unnumbered paragraph

The SLP is accordingly dismissed. T.N.A. Petition dismissed.