THE SPECIAL LAND ACQUISITION OFFICER, KALINADAI (HYDRO-ELECTRIC) PROJECT, DANDALI, UTTAR KANNADA DISTRICT versus VASANT GUNDU BALE

Decided
31 October 1995
Judges listed
K. RAMASWAMY, B.N. KIRPAL (as the open data lists them; this may not name the whole bench)
Disposal
Appeal(s) allowed

Citations

Official
[1995] SUPP. 4 S.C.R. 614 · 1995 INSC 656

Cited by

We found no other Supreme Court judgment we hold that cites this one.

Counted only in the Supreme Court judgments we hold whose text we could read, not in High Court judgments. We match each citation to a judgment automatically, so a citation we cannot match is not counted. "Cited" says only that a judgment refers to this one, not whether it followed, distinguished or overruled it.

The Court's text

Paragraphs from our copy of the Supreme Court Reports print, with the Court's own paragraph numbers, the printed page and, where printed, the margin letter. The Court did not number this judgment's paragraphs, so they are listed by page. Link to paragraph N with #para-N.

Unnumbered paragraph

Notification under Section 4(1) of the Land Acquisition Act, 1894 (for short, 'the Act') acquiring an extent of six acres 21 Gunthas of land for Hydro Electric Project was published on Augost 12, 1975. The Land Acquisition Officer awarded compensation at various rates for wet land, dry land, garden land and phot-kharab land. On reference under section 18, the Civil Court enhanced the compensation at a uniform rate of Rs. 15,520 per acre. On appeal under Section 54, the High Court enhanced the compensation to Rs.18,000 per acre. Dissatisfied therewith, the State Government has filed this appeal by special leave.

p. 615, margin B

Unnumbered paragraph

Sri Veerappa, the learned counsel for the Slate, has contended that the High Court committed grave error of law in recording a finding that lands were possessed of potential value for building purposes. We find no force in the contention. It is seen that when 7,800 tenaments were constructed in the project area, it would be clear that a township had come into existence. It is an admitted fact that the land under acquisition is about the township. It is also an admitted fact that in Ext. A-12 sanction was obtained on September 13, 1973 for conversion of agricultural lands into urban lands of the layout and sale of plots which could not take place due to the fact that mud was dumped on this land. Consequently, the sanction came to be cancelled by the Assistant Commissioner. Be that as it may, the High Court on the basis of the rental value had determined compensation at the rate of Rs. 1200 per acre applying the multiplier of 15 and "rrived at the net income at Rs. 18,000 per acre. It is now settled law that the uniform rate of multiplier of 10 is being applied for the lands acquired even in the State of Karnataka. Even acceding the multiplier of 12 as held by this Court in Special Land Acquisition .Officer, Davangree v. P. Vecrabhadarappa and (1984] 2 SCC 120, the claimant cannot get more than Rs. 14,000 per acre. Since the State had not filed the appeal against tb.e enhanced compensation under Section 26, of the Act, amount awarded by the Reference Court had become final. Therefore, this Court cannot interfere with and reduce the compensation less than the amount awarded by the Civil Court. The enhanced compensation stands upheld at the rate of Rs. 15,520 per acre \\;th solatium at the rate of 15% and 15% interest on the enhanced compensation.

pp. 615–616, margin D

Unnumbered paragraph

The appeal is accordingly allowed but in the circumstances without costs. R.P. Appeal allowed.

p. 616, margin A