Certo Is this judgment real?
Beta, Supreme Court only. We check Supreme Court of India judgments only for now: a High Court citation reads "Not in our corpus", which never means it does not exist.

Supreme Court of India

STATE OF ARUNACHAL PRADESH versus M/S. DAMINI CONSTRUCTION

Decided
28 February 2007
Judges listed
A.K. MATHUR (as the open data lists them; this may not name the whole bench)
Disposal
Dismissed

Citations

Official
[2007] 3 S.C.R. 416 · 2007 INSC 230
Also cited as
  • (2007) 10 SCC 742 (19 citing judgments)
  • (2007) 3 SCALE 576 (2 citing judgments)

Learned from how other judgments cite this one, in their text or in the official Supreme Court Reports' lists of cases they refer to: each is cited this way by at least two judgments, and at least twice as often as any other citation to this judgment in that report. We hold no commercial reporter's text, only these citation strings.

Cited by

Cited in 2 other Supreme Court judgments we hold.

Counted only in the Supreme Court judgments we hold whose text we could read, not in High Court judgments. We match each citation to a judgment automatically, so a citation we cannot match is not counted. "Cited" says only that a judgment refers to this one, not whether it followed, distinguished or overruled it.

The Court's text

Paragraphs from our copy of the Supreme Court Reports print, with the Court's own paragraph numbers, the printed page and, where printed, the margin letter. Link to paragraph N with #para-N.

Paragraph 1

Leave granted in both the Special Leave Petitions.

p. 418, margin F

Paragraph 2

Since the question of law involved in both the appeals is common, they are disposed of by this common judgment. For the sake of convenience, the facts stated in Civil Appeal arising out ofS.L.P.(c) No.14804 of2005 are ·. taken into consideration.

p. 418, margin G

Paragraph 3

This appeal is directed against the order passed by learned Single Judge of the Gauhati High Court, Itanagar Bench in Writ of 2004 whereby learned Single Judge set aside the order passed by the Deputy Commissioner cum District Judge, Papum Yupia in Miscellaneous Application No. I 0 of 2004 condoning making application under Section 34 of the Arbitration and 1996 (hereinafter to be referred to as 'the Act' ), being not maintainable. the order dated 15.9.2004 was set aside and the writ petition Aggrieved against this order passed by the High Court of Bench, State of Arunachal Pradesh has preferred the present

pp. 418–419, margin H

Paragraph 4

Brief facts which are necessary for disposal of this the respondent herein entered into a contract agreement bearing 1992-93 with the State of Arunachal Pradesh in Public Works executing the contractual work of construction of road bridges. the work in question although was initially fixed at Rs.77.43 basis of the post tender negotiation by and between the parties, the work was re-fixed at Rs. I. 15 crores. The work was to be two calendar years from the date of commencement of the commenced on 10.4. 1993 and it was completed in March, 1999. the petitioner-respondent herein the delay in execution of the to deviation from the original scope of work and several obstructions difficulties including delay in approval of the design and drawings in making payment against running accounts bills from time respondent herein raised bill for the contractual work which respondent was refused to be paid due to certain arbitrary reasons. Such refusal gave rise to a dispute and accordingly, arbitration. The respondent then approached the Court under the Act which was numbered and registered as Arbitration Case and the same was disposed of by the High Court appointing adjudicate the dispute between the parties. One arbitrator was 18.10.200 I but subsequently that arbitrator was changed arbitrator. On 12. 10.2003 the arbitrator passed an interim Rs.65,52,878/- with simple interest to be calculated if the award not paid within 60 days from the date of the award. However, limitation prescribed under Section 34(3) of the Act for setting expired in the meantime. The appellant then wrote a letter to review of the award and also sought clarification in respect 2.4.2004. On I 0.4.2004 the arbitrator by his letter stated jurisdiction to entertain the request for review of the award and that the award dated 12.10.2003 was in fact a final award issues involved. On 21.6.2004 the respondent- petitioner filed an application for execution of the interim award dated 12.10.2003 before the Deputy Commissioner. On 6.8.2004 the appellant filed an application under Section 34 of the Act for setting aside the award dated 12.10.2003 together with an application under Section 5 of the Limitation Act read with Section 34(3) of the Act for condonation of delay in filing the application for setting aside the award. The said application was entertained and was fixed for hearing on condonation of delay after 15 days. Aggrieved against this order, a writ petition was filed by the respondent herein but the same was disposed of by the High Court with the observation that as the matter was pending before the court below it would not be appropriate to interfere at this stage and left the Deputy Commissioner to decide the matter. The Deputy Commissioner, Papum Pare, Itanagar by the impugned order dated 15.9.2004 decided the application condoning the delay in preferring the application under Section 34 of the Act by the appellant. Aggrieved against this order, the present writ petition was filed by the respondent herein. It is the legality of this order which was challenged before the High Court. Learned Single Judge of the High Court after hearing both the parties came to the conclusion that the order passed by the Deputy Commissioner in condoning the delay was not correct and it took the view that under section 34 of the Act, there was a delay of seven months from the date of first order and a delay of six months from the date of second order.

pp. 419–420, margin B

Paragraph 5

The plea of the appellant- State before the court below was that the award was passed on 12.10.2003 and a copy was received on 23.10.2003. As such, the period of limitation started from 23 .I 0.2003. Since the letter was sent by the appellant to the arbitrator on 2.4.20043 for review of the award and a reply thereof was received on 10.4.2004 whereby the matter was clarified by the arbitrator, therefore, the cause of action accrued in favour of the appellant on 10.4.2004 and application under Section 34 of the Act was filed on 6.8.2004 i.e. within three months and the extended period of one month, therefore, it was within limitation. Though this contention prevailed before the trial court but the same failed before the High Court on the ground that the cause of action accrued to the appellant on 23.10.2003 when the appellant received the copy of the award and the letter which was written on 2.4.2004 was totally misconceived. The interim award was final with regard to the claims raised therein, therefore, the whole exercise undertaken by the appellant was totally misconceived. Hence, learned Single Judge allowed the writ petition and set aside the order of the trial court. Aggrieved against this order passed by the learned Single Judge, the present appeal was filed,

pp. 420–421, margin E

Paragraph 6

We have heard learned counsel for the parties and record. Learned counsel for the appellant tried to persuade us cause of action has arisen to the appellant on l 0.4.2004 when received from the arbitrator and therefore, the appellant was entitled the period of limitation from the date of receipt of the letter from and if the limitation was to start from I 0.4.2004 then the appellant to move an application for setting aside of the award under section Act within three months and the extended period of one month appellant having filed the application on 6.8.2004, therefore, it was The submission of learned counsel for the appellant is totally misconceived and it cannot be accepted. A perusal of the interim award arbitrator clearly shows that it was final to the extent of the claims decided therein and it may be relevant to refer to the concluding portion which reads as under : "I further direct that the awarded amount is indicated with the interest, wherever shown till the date of amounting to Rs.65,52,878.00 (Rupees Sixty five lakhs thousand Eight hundred seventy eight only), shall be Respondents to the Claimant within 60 days from the award, failing which a simple interest on the unpaid amount (Eighteen percent) per annum shall be payable to the Claimant respondents after 60 days of this interim award." Therefore, this interim award which did not mince any word and the amount after discussing the claims in detail and finally calculated amount under each of the claims. Therefore, there was no confusion award. It was absolutely thoughtlessness on the part of the appellant written a letter after six months i.e. on 2.4.2004 seeking review award to the following effect: "While submitting the request for review the case, requested that your honour may kindly consider (sic.) points regarding mode of payments, if at all, the payment made, as the award given by your honour is for the interim (a) Whether payment is to be made directly to Construction Co. or through honourable court. (b) In case, the payment is to be made directly Construction Co., an equivalent Bank Guarantee Nationalized Bank shall be required from the Contractor be an interim payment and final verdict awaited. Submitted for your kind consideration please." Firstly, the letter had been designed not strictly under section because under Section 33 of the Act a party can seek computation of e1rnrs, or clerical or typographical errors of a similar nature occurring in the award with notice if agreed between the parties, a party may request the arbitral an interpretation of a specific point or part of the award. which was moved by the appellant does not come within falling under Section 33(1) of the Act. It was designed as seeking review of the award. Since the Tribunal had no merit, therefore, the application moved by the appellant misconceived. Secondly, it was prayed whether the payment directly to the respondent or through the Court or that the be asked to furnish Bank guarantee from a nationalized interim award, till final verdict was awaited. Both these were not within the scope of Section 33. Neither review the prayer which had been made in the application had Section 33 of the Act. The prayer was with regard to the When this application does not come within the purview Act, the application was totally misconceived and accordingly by communication dated I 0.4.2004 replied to the following "However, for your benefit I may mention here that of the Act of 1996, the issues/ claims that have the interim award dated 12.10.2003 are final cannot be gone into once again at the time award." Therefore, the reply given by the arbitrator does not give action to the appellant so as to move an application under the Act. In fact, when the award dated 12.10.2003 was passed with the appellant was either to have moved an application within three months as required under sub-section (3) of the extended period of another 30 days. But instead misconceived application was filed and there too the prayer and with regard to mode of payment. The question of review was totally A ~ misconceived as there is no such provision in the Act for review of the award by the arbitrator and the clarification sought for as to the mode of payment is not contemplated under Section 33 of the Act. Therefore, in this background, the application was totally misconceived and the reply sent by the arbitrator does not entitle the appellant a fresh cause of action so as to file an application under Section 34(3) of the Act, taking it as the starting point of limitation from B the date of reply given by the arbitrator i.e. 10.4.2004.

pp. 421–423, margin A

Paragraph 7

Thus, in this background, the view taken by learned Single Judge appears to be justified and there is no ground to interfere in this appeal. Consequently, there is no merit in both the appeals and the same are dismissed C with no order as to costs. B.B.B. Appeals dismissed.

p. 423