Supreme Court of India

UNION OF INDIA AND ORS. versus AJAIB SINGH AND ORS.

Decided
20 September 1995
Judges listed
A.M. AHMADI, S.C. SEN (as the open data lists them; this may not name the whole bench)
Disposal
Case Allowed

Citations

Official
[1995] SUPP. 3 S.C.R. 831 · 1995 INSC 587

Cited by

We found no other Supreme Court judgment we hold that cites this one.

Counted only in the Supreme Court judgments we hold whose text we could read, not in High Court judgments. We match each citation to a judgment automatically, so a citation we cannot match is not counted. "Cited" says only that a judgment refers to this one, not whether it followed, distinguished or overruled it.

The Court's text

Paragraphs from our copy of the Supreme Court Reports print, with the Court's own paragraph numbers, the printed page and, where printed, the margin letter. The Court did not number this judgment's paragraphs, so they are listed by page. Link to paragraph N with #para-N.

Unnumbered paragraph

SEN, J. Special leave granted.

p. 832, margin D

Unnumbered paragraph

This is a case of acquisition of land under the Requisitioning and Acquisition of Immovable Property Act, 1952. The short question that falls for determination is whether the arbitrator had erred in enhancing the amount of compensation to the flat rate of Rs. 300 per Marla and awarding solatium @30% per annum and interest @9% per annum for the first year and thereafter 15% per annum for the subsequent years from the date of possession of the property.

p. 832, margin E

Unnumbered paragraph

Land measuring 26.08321 acres in village Daulatpur, Tehsil Pathankot, District Gurdaspur was acquired under the Requisitioning and acquisition of Immovable Property Act, 1952 by the Special Land Acquisition Collector by a notification issued on 30th October, 1969. The competent authority awarded compensation for the acquired land @ Rs. 60 per Marla. After a long lapse of time, the question of compensation was referred to an arbitrator.

p. 832, margin F

Unnumbered paragraph

Mr. Goswami, on behalf of the appellants, has argued that there was no dispute as to the quantum of compensation between the respondents and the appellants and the compensation was actually paid to the respondents and the respondents duly accepted the compensation without any protest. Under Rule 9 of the Requisitioning and Acquisition of Immovable Property Rules, 1953, the competent authority can pay compensation only after entering into an agreement in Form-K. Mr. Goswami has contended that in the instant case, compensation was paid. There was no dispute as to the quantum of compensation. An agreement in Form-K was entered into with the respondents before payment of the compensation.

pp. 832–833, margin H

Unnumbered paragraph

However, there is no averment in the pleading that an agreement in Form-K was entered into by and between the competent authority and the respondents. But, there is no dispute that eight years after compensation was paid, the writ-petitioners raised the dispute as to the quantum of compensation and made an application for referring the dispute to the arbitrator. On 30th March, 1987, the Additional District Judge, Gurdaspur, as arbitrator awarded compensation at flat rate of Rs. 300 per Marla. The arbitrator also awarded solatium @30% and interest @ 9% per annum for the first year from the date of acquisition. i.e., 31.10.1969 and 15% per annum for the subsequent years till the amounts were realised.

p. 833, margin B

Unnumbered paragraph

Aggrieved by this award, the Government preferred appeals to the High Court of Punjab and Haryana. The appeals were dismissed by a Single Judge of the High Court on 30th July, 1987. Further appeals were filed before the Division Bench of the High Court. Those appeals were dismissed on 5th April, 1990.

p. 833, margin D

Unnumbered paragraph

These Special Leave Petitions were moved in this Court on 21st December, 1990. The dispute before this Court is not about the quantum of the compensation fixed by the Additional District Judge as arbitrator on 30th March, 1987. Notice was issued only on the question of solatium and interest. Mr. Goswami, on behalf of the appellants, has contended that there is no basis for granting solatium at 30% and interest at 9% for the first year and 15% for the subsequent years. He has pointed out that the Government was not at fault in this case for the delay in appointment of the arbitrator. Since the compensation amount fixed by the Special Land Acquisition Collector had been accepted without any dispute, there was no scope for referring any dispute to an arbitrator under Section 8(1)(b) of the Act. Therefore, the Government should not be held responsible for the delay in the instant case.

pp. 833–834, margin F

Unnumbered paragraph

The contention on behalf of the appellant will have to be upheld in the facts of this case. Unlike the Land Acquisition Act, there is no provision in the Requisitioning and Acquisition of Immovable Property Act for payment of solatium and interest. Solatium and interest have been awarded in the interest of justice in certain cases. But in the absence of special circumstances, such award of interest and solatium cannot be justified under the provisions of the Requisitioning and Acquisition of Immovable Property Act.

p. 834, margin A

Unnumbered paragraph

On behalf of the respondents, Mr. R.C. Pathak has drawn our attention to a judgment of this Court in the case of Union of India v. Hari Krishan Khosla, (1992) 2 SC No. 621. This was also a case under Requisitioning and Acquisition of Immovable Property Act, 1952. The ultimate decision in this case goes against the contention of Mr. Pathak. In S.L.P. (C) No. 1780/1991, the award of 15% solatium and 6% interest on enhanced compensation was set aside. In C.A. No. 4688-94/1989 and C.A. No. 2674-85/1989, award of solatium and interest was upheld because no arbitrator was appointed for a period of sixteen years.

p. 834, margin C

Unnumbered paragraph

In the instant case, it has not been established on behalf of the respondents that there was any delay in the appointment of arbitrator on the part of the appellant. There is nothing to show that the respondents had demanded appointment of arbitrator or had disputed the amount of compensation paid by the Special Land Acquisition Collector. It is true that arbitrator was ultimately appointed at the instance of the respondent. But there is nothing to indicate that the respondents had earlier disputed the amount of compensation or had demanded appointment of arbitrator. There is no dispute that the compensation was accepted. It is for the respondents to establish that it was accepted under protest. These facts have not been established by the respondents.

p. 834, margin D

Unnumbered paragraph

It is true, in the instant case, there had been no delay on the part of the Government in referring the matter to an arbitrator. It has not been stated by the respondents that they had demanded appointment of an arbitrator, when they found that the compensation amount was inadequate. No letter or any other document has been annexed to the writ petition or produced before this Court in support of the case of the respondents.

p. 834, margin G

Unnumbered paragraph

Therefore, we are of the view that in the facts of this case, the arbitrator was in error in allowing solatium and interest without coming to a decision as to the existence of any dispute and the failure of the Government to refer the matter to an arbitrator. The appeals, therefore, are partly allowed. The order relating to payment of solatium and interest is set aside. There wi. · no order as to costs. G.N. Appeals partly allowed.

p. 835, margin A