YUNUS (BABOOBHAI) A HAMID PADVEKAR versus STATE OF MAHARASHTRA THROUGH ITS SECRETARY AND ORS.

Decided
28 January 2009
Judges listed
ARIJIT PASAYAT (as the open data lists them; this may not name the whole bench)
Disposal
Dismissed

Citations

Official
[2009] 1 S.C.R. 689 · 2009 INSC 84
Also cited as
  • (2009) 3 SCC 281 (6 citing judgments)
  • JT 2009 (3) SC 487 (2 citing judgments)

Learned from how other judgments cite this one, in their text or in the official Supreme Court Reports' lists of cases they refer to: each is cited this way by at least two judgments, and at least twice as often as any other citation to this judgment in that report. We hold no commercial reporter's text, only these citation strings.

Cited by

We found no other Supreme Court judgment we hold that cites this one.

Counted only in the Supreme Court judgments we hold whose text we could read, not in High Court judgments. We match each citation to a judgment automatically, so a citation we cannot match is not counted. "Cited" says only that a judgment refers to this one, not whether it followed, distinguished or overruled it.

The Court's text

Paragraphs from our copy of the Supreme Court Reports print, with the Court's own paragraph numbers, the printed page and, where printed, the margin letter. Link to paragraph N with #para-N.

Paragraph 1

Leave granted.

p. 691

Paragraph 2

Challenge in this appeal is to the order passed by a Division Bench of the Bombay High Court dismissing the Writ Petition filed by the appellant on the ground that it was highly belated. It also noted that the appellant had received compensation in respect of the land which was acquired.

p. 691

Paragraph 3

Background facts in a nutshell are as follows: In the year 1971 Maharashtra Industrial Development· Corporation (in short 'MIDC') acquired about 1250 acres of agricultural land situated at four villages in Ratnagiri district of G Maharashtra. Thirty eight acres of land belonging to the appellant were acquired. It is the stand of the appellant that out of the acquired area, about 50% was under paddy cultivation and 25% was under cultivation of mango crops. In the appellant's land about 175 mango trees were there. In the year 1973, the Revenue and Forest Department of the Maharashtra Government passed a resolution inter-alia deciding to take steps in respect of surplus acquired land which remained unutilized for a period of three years from the date of taking over possession for resumption of such lands in accordance with the applicable rules and orders. In 1974, a Writ Petition was filed by the appellant challenging the Notification for acquisition and an arrangement was worked out in which 20 acres of appellant's land out of 38 acres were released. The lands were acquired for a Govt. company-Balco for setting up a manufacturing unit. Since Balco did not set up any unit, license issued to it was cancelled. In the year 1982, appellant claims to have made representations alongwith similarly situated land owners for restoration of the acquired land to the original owners. In the year 1983, compensation was paid to 686 land owners. In 1984, again the appellant made a representation to the Collector of Ratnagiri for release of the land. On 20. 7.1989 a Committee was appointed by the Legislative Assembly for consideration of the proposal for handing back the acquired land to the original owners. Certain recommendations were made by the said Committee. On 20.8.1992 the land acquired for Balco was allotted to another industrial group. Subsequently, the State Government asked the industrial group not to continue the construction activities in view of pendency of cases. On 12.11.2002, representations were again made to hand back the land not utilized. It was the specific stand of the appellant that in view of Section 39(2a) of the Maharashtra Industrial Development Act, 1961 (in short the 'Act') the land should be restored. The High Court dismissed the writ petition on the ground that it was highly belated.

pp. 691–692

Paragraph 4

In support of the appeal, learned counsel for the appellant stated that the appellant was all through representing to the authorities and because of the recommendations by the Committee, the appellant waited for some time and ultimately when no worthwhile action was taken, he filed the writ petition.

p. 692, margin G

Paragraph 5

Learned counsel for the respondent on the other hand A supported the judgment of the High Court.

p. 693

Paragraph 6

It is pointed out that the recommendations made in terms of the resolution were not accepted by the Government. It was decided that since definite policy has been formulated the land is to be utilized for the industrial development, the same cannot be surrendered to the original owners for cultivation purposes. It is also pointed out that the so called representations do not in any way assist the appellant to explain the long delay in filing the writ petition.

p. 693

Paragraph 7

It is also pointed out that Section 39(2a) is applicable only in respect of the undeveloped land, and in the instant case the. land in question is developed land.

p. 693

Paragraph 8

Delay or laches is one of the factors which is to be borne D in mind by the High Courts when they exercise their discretionary powers under Article 226 of the Constitution of India, 1950 (in short the 'Constitution'). In an appropriate case the High Court may refuse to invoke its extraordinary powers if there is such negligence or omission on the part of the applicant E to assert his right as taken in conjunction with the lapse of time and other circumstances, causes prejudice to the opposite party. Even where fundamental right is involved the matter is still within the discretion of the Court as pointed out in Durga Prasad v. Chief Controller of Imports and Exports (Al R 1970 SC 769). Of course, the discretion has to be exercised judicially F and reasonably.

p. 693

Paragraph 9

What was stated in this regard by Sir Barnes Peacock in Lindsay Petroleum Company v. Prosper Armstrong Hurde etc. (1874) 5 PC 221 at page 239 was approved by this Court G in Moon Mills Ltd. v. Industrial Courts (AIR 1967 SC 1450) and Maharashtra State Transport Corporation v. Ba/want Regular Motor Service (AIR 1969 SC 329), Sir Barnes had stated: "Now the doctrine of laches in Courts of Equity is not an H arbitrary or technical doctrine. Where it would practically unjust to give a remedy either because the party has, by his conduct done that which might fairly regarded as equivalent to a waiver of it, or where by conduct and neglect he has though perhaps not waiving that remedy, yet put the other party in a situation in which it would not be reasonable to place him if the remedy were afterwards to be asserted, in either of these cases, lapse of time and delay are most material. But in every case, an argument against relief, which otherwise would be just, if founded upon mere delay, that delay of course amounting to a bar by any statute of limitation, the validity of that defence must be tried upon principles substantially equitable. Two circumstances always important in such cases are, the length of the delay and the nature of the done during the interval which might affect either party cause a balance of justice or injustice in taking the course or the other, so far as relates to the remedy."

pp. 693–694

Paragraph 10

It would be appropriate to note certain decisions of Court in which this aspect has been dealt with in relation with Article 32 of the Constitution. It is apparent that what has been stated as regards that Article would apply, a fortiori, to Article 226. It was observed in R.N Bose v. Union of India (AIR 1970 SC 470) that no relief can be given to the petitioner who without any reasonable explanation approaches this Court under Article 32 after inordinate delay. It was stated that though Article 32 itself a guaranteed right, it does not follow from this that it was the intention of the Constitution makers that this Court should disregard all principles and grant relief in petitions filed after inordinate delay.

p. 694, margin D

Paragraph 11

It was stated in State of M.P. v. Nandlal (Al R 1987 251) that the High Court in exercise of its discretion does ordinarily assist the tardy and the indolent or the acquiescent and the lethargic. If there is inordinate delay on the part of petitioner and such delay is not satisfactorily explained, High Court may decline to intervene and grant relief in exercise A + of its writ jurisdiction. It was stated that this rule is premised on a number of factors. The High Court does not ordinarily permit a belated resort to the extraordinary remedy because it is likely to cause confusion and public inconvenience and bring in its trail new injustices, and if writ jurisdiction is exercised after unreasonable delay, it may have the effect of inflicting not only hardship and inconvenience but also injustice on third parties. It was pointed out that when writ jurisdiction is invoked, unexplained delay coupled with the creation of third party rights in the meantime is an important factor which also weighs with the High Court in deciding whether or not to exercise such jurisdiction.

pp. 694–695, margin G

Paragraph 12

In view of the aforesaid position we are not inclined to interfere in this appeal which is dismissed accordingly. - D ... G.N. Appeal dismissed .

p. 695