Supreme Court of India

DELHI DEVELOPMENT AUTHORITY, N.D. & ANR. versus JOINT ACTION COMMITTEE, ALLOTTEE OF SFS FLATS & ORS.

Decided
13 December 2007
Judges listed
S.B. SINHA (as the open data lists them; this may not name the whole bench)
Disposal
Disposed off

Citations

Official
[2007] 13 S.C.R. 811 · 2007 INSC 1299
Also cited as
  • (2008) 2 SCC 672 (47 citing judgments)
  • AIR 2008 SC 1343 (9 citing judgments)
  • (2008) 1 SCC(CIV) 684 (3 citing judgments)
  • MANU/SC/0202/2008 (2 citing judgments)

Learned from how other judgments cite this one, in their text or in the official Supreme Court Reports' lists of cases they refer to: each is cited this way by at least two judgments, and at least twice as often as any other citation to this judgment in that report. We hold no commercial reporter's text, only these citation strings.

Not shown
1 other citation string that other judgments attach to this one, on evidence too thin or too divided to publish.

Cited by

Cited in 5 other Supreme Court judgments we hold.

Counted only in the Supreme Court judgments we hold whose text we could read, not in High Court judgments. We match each citation to a judgment automatically, so a citation we cannot match is not counted. "Cited" says only that a judgment refers to this one, not whether it followed, distinguished or overruled it.

The Court's text

Paragraphs from our copy of the Supreme Court Reports print, with the Court's own paragraph numbers, the printed page and, where printed, the margin letter. The Court did not number this judgment's paragraphs, so they are listed by page. Link to paragraph N with #para-N.

Unnumbered paragraph

H S.B. SINHA, .J. l. Leave granted in all the Special Leave Petitions.

p. 820

Unnumbered paragraph

,.

p. 821

Unnumbered paragraph

CIVIL APPEAL NOS. 6666, 6667, 6668-6698, 6700-6732 & A • 6733 of 2000 CIVIL APPEALS@ SLP (CIVIL) NOS. 25385 OF 2005, 1003, 8033 OF 2006 AND 13512 OF 2006:

p. 821

Unnumbered paragraph

2. This batch of appeals arising out of a judgment and order dated 23.07.1999 passed by a Division Bench of the Delhi High Court, inter alia, in Writ Petitions No. 793of1993 as also a judgment and order dated 22.07.2005 passed by a Full Bench of the Delhi High Court in Letters Patent Appeal Nos. 844 of2003 etc. were heard together and are being disposed of by this common judgment.

p. 821

Unnumbered paragraph

FACTS:

p. 821

Unnumbered paragraph

3. Delhi Development Authority (for short, 'the Authority) has been constituted under the Delhi Development Act, 1957 (for short, 'the Act'). Indisputably, it develops different areas in the town of Delhi and constructs

p. 821

Unnumbered paragraph

houses for all groups of people. :) 4. Principally it allocates flats under six different schemes viz : (i)

p. 821

Unnumbered paragraph

Self Financing Scheme (SFS); (ii) Higher Income Group Scheme (HIG Scheme); (iii) Middle Income Group Scheme (MIG Scheme); (iv) Lower Income Group Scheme (LIG Scheme), (v) Janata Scheme; and (vi) Expandable Housing Scheme.

p. 821

Unnumbered paragraph

5. The flats constructed and allocated under the SFS Scheme are distinct and different from the other five schemes launched by the

p. 821

Unnumbered paragraph

Authority. We shall advert to the said distinction a little later. ~ 6. Suffice, however, it to say that not only costs of such schemes are calculated on different basis but the rights and stipulated liabilities thereunder are also different. Cost of flats vary from scheme to scheme. Under one of the schemes, applications were invited by the Authority from 22.12.1992 to 11.01.1993.

p. 821

Unnumbered paragraph

7. We may notice some of the provisions containing the terms and G conditions on the basis whereof such an offer was made .

p. 821

Unnumbered paragraph

"5.10 the details of the flats and tentative cost etc. are available in Annexure-B. The cost of the flats mentioned therein is tentative and subject to revision on account of escalation in the value ofland and cost of construction. Please note that there is a possibility upward revision of the tentative cost. 5 .11. Those who are successful for a ready built flat will be called upon to make the payment in lump sum within 60 days. Others who are successful for a flat where the work is already in progress will be asked to deposit within 30 days a specified percentage anything upto 90% of the estimated disposal price representing expenditure already made and the amount required for construction of flats in next 3 to 4 months. Applicants successful for allocations are asked to pay 25% the estimated cost of the flat way of 1st instalment payable within 30 days. In each of the 60 days time is further given to remit the amount with prescribed interest. 11.2. The demand-cum-allocation letters issued will indicate prescribed dates by which the payments will be required to made. The demand letter for final instalment for the flats in progress and new allocations will be issued separately and this may include the possible increase in the cost of the flat. No separate letters will be issued for any of the subsequent instalments. It be obligatory on the part of the allocatees to make the payments and deposit the requisite documents before the due dates indicated. In the event of default the allocation/allotment of the flat in scheme will be liable to be cancelled. If submission of documents as demanded are delayed, maintenance charges will be leviable provided the delay in submission of documents is regularized. 12.2. If the allotment of flat is cancelled (either on the allottee's own request or due to the non-fulfilment of the terms and conditions of allocation by the allottee) after the expiry of I, 2, 3 and 4 months from the date of issue of demand-cum-allocation letter, interest calculated@ 12% p.a. for the 1st month and 18% p.a. for 2nd, 3rd and 4th month on the amount demanded in the demand letter shall be charged in addition to the amount of penalty specified above. 14.1. The allottee shall be entitled to take delivery of the possession only after he has completed all the formalities, paid all dues and furnished/executed all the documents as required in the allotmentcum-demand letter of the Delhi Development Authority."

pp. 821–823

Unnumbered paragraph

8. Appellants in the first batch of cases and the respondents in the second batch (hereinafter referred to as 'the registrants') applied for allocation of flats under the SFS Scheme. The said scheme was floated in terms ofltem No.112of1992. For the said purpose, brochures are issued. Those who desired to have allocation of such flats were asked opt therefor at three different places. Allocation of flats under the said Scheme is made upon 90% payment of the estimated costs. However, allotment is made on draw of specific number of flats. Allocation of flats may be made in respect of areas, floors and/or the pockets. On receipt of the letter of demand-cum-allocation by the registrant, the schedule payment commences. Estimated cost for construction is calculated on the basis of the value of the land and likely cost of constructions.

p. 823, margin A

Unnumbered paragraph

9. The letter of demand-cum-allocation issued to successful registrants contains a condition which may be noticed for the purpose these cases and read as under :

p. 823, margin D

Unnumbered paragraph

"4. The amount demanded should be paid on or before the due date mentioned in para 2 and 3 above. Extension of time for making payment of the amount demanded in column 7 of para above upto a maximum period of 90 days from the due date admissible. An allottee need not apply for extension but he will have to pay interest @ 12% p.a. for the first month and @ 18% p.a. for the subsequent period. In case payment of the amount asked for in the demand letter is not made within 90 days of the due date, the allotment shall stand cancelled automatically. However, cancellation due to non-payment of first 4 instalments during the stipulated period can be got restored on payment of dues with interest along with cancellation and restoration charges for each cancellation due to non-payment, subject to availability of the allocated flat. The cancellation due to non-payment of final instalment within 120 days of the date of issue (letter of the block date) of the demand letter for 5th instalment shall not be restored under any circumstances." A I 0. It may be useful to notice some other clauses containing terms and conditions of allocation, which are as under :

pp. 823–824, margin D

Unnumbered paragraph

"!.No separate demand letters will be issued for 2nd, 3rd and 4th instalments. It will be obligatory on your part to make the payment before the due date indicated at page- I; failing which the allocation is liable to be cancelled. 2. The estimated cost of the flats as given in this letter is provisional and subject to revision on the completion of the flat. Any price

p. 824

Unnumbered paragraph

difference between the estimated cost and the cost as it comes out on completion as per costing formula then in vogue would have to be paid along with the 5th and final instalment. There would be no review of the cost of the flat in the intermining period. Interest@ 7% on the amount deposited will be payable for the period beyond

p. 824

Unnumbered paragraph

3 Yz years to the date of issue of possession letter if the construction of the houses is not completed by then.

p. 824, margin C

Unnumbered paragraph

3. The amount demanded should be paid on or before the stipulated due date failing which the allotment shall be liable to be cancelled without notice. In case, due to unavoidable reasons, the

p. 824, margin D

Unnumbered paragraph

allottee is not able to make the payment within the due time, then he must ensure that his acceptance of the allotment reaches the Housing Department before the due date of payment with a request for exiension."

p. 824, margin D

Unnumbered paragraph

11. Registrants are said to have defaulted resulting in purported automatic cancellation of their allotments. Show cause notices were issued to them. Some of them allegedly expressed their difficulties in regard thereto.

p. 824, margin E

Unnumbered paragraph

Decisions impugned

p. 824, margin F

Unnumbered paragraph

12. TI1e Vice-Chairman of the appellant who is said to be delegated with the power of the Authority to which reference would be made hereinafter took a policy decision which is reflected from Office Order issued on 16.8.1996, the relevant clauses whereof are :

p. 824, margin G

Unnumbered paragraph

"2. With the approval ofL.G. a decision was taken that the current price for South Delhi flats will be worked out by adding a surcharge of 20% from the price worked out as per old formula. The approval ofL.G. to this decision was granted

pp. 824–825, margin G

Unnumbered paragraph

on 12.07.1996. . There are presently cases in the Housing Department where there have been delays in the making of the payments of the flats allocated/allotted in South Delhi under SFS. Before the aforesaid revision took place, delays of one year or so were being regularised with usual charges, i.e., on payment of 18% interest per annum and restoration charges, etc. in few cases where delays are unusually long, current price has also been

p. 825, margin A

Unnumbered paragraph

demanded."

p. 825, margin C

Unnumbered paragraph

13. The aforementioned Office Order dated 16.8.1996 was reiterated in a resolution dated 27.8.1996 wherein a further decision was taken to impose a surcharge of 20% "over and above" disposal price only in respect of registrants who had been allotted flats in South Delhi. The said decision was taken to balance the reduced cash flow of the Authority. It reads as under:

p. 825, margin C

Unnumbered paragraph

"I. On the basis of the aforesaid resolutions of the Authority, 50% flats are proposed to be offered to the public. It is also being proposed to offer to public the unavailed flats if any out the 50% flats being reserved for Govt. organisations/PSUs. In this manner, number of flats to be offered to the public can be beyond 50%.

p. 825, margin D

Unnumbered paragraph

:xxx xxx xxx

p. 825, margin E

Unnumbered paragraph

4. To balance the reduced cash in-flow because of the proposed discount it will be necessary to charge premium in the areas where the real value in the market ofDDA flats is much more than what DDA is charging as per its costing formula in the demand letters. It would be in the fitness of thing to charge premium of 20% over the disposal cost worked out for the

p. 825, margin F

Unnumbered paragraph

flats in South Delhi SFS."

p. 825, margin G

Unnumbered paragraph

14. Yet again, on 5.11.1998, a purported clarification was issued regard to regularization of flats where there had been delay in payment of first four instalments, stating: A "While issuing allocation/allotment letters the registrants of various schemes announced by DDA, a demand is raised from the concerned allottees specifying the amounts to be paid with due date of payment. However, sometimes on account of the problem faced

pp. 825–826, margin G

Unnumbered paragraph

by the concerned allottees the payment received by the DDA are later than the scheduled date. Such cases are usually examined on merits and the delay is regularised if there is merit in the case as non-regularisation of delays in deserving cases may be resulted by the allottees. The following shall be the rules applicable to the allottees of all category of flats in case there payments are delayed and are regularised by the competent authority. A. Competent Authority to regularise the delay: Period of delay Designation (i) Upto 30 days Jt./Dy. Directors (ri) Beyond 30 days but

p. 826

Unnumbered paragraph

upto 90 days Director (Housing)

p. 826, margin B

Unnumbered paragraph

(rii) Beyond 90 days but Commissioner upto 1 year (Housing)

p. 826, margin B

Unnumbered paragraph

(iv) Beyond 1 year but upto Principal

p. 826, margin E

Unnumbered paragraph

year 6 months Commissioner (v) More than 1 year

p. 826, margin E

Unnumbered paragraph

r ,

p. 826, margin E

Unnumbered paragraph

6months Vice-Chainnan B. Price of the Flat : (i) If the allocated/allotted flat is in South Delhi where the construction has been undertaken by the South East Zone and South West Zone of the Engineering Wing Except Dwarka (being in West Delhi) the Price of the flat if restored, would be "Old Cost"

p. 826, margin E

Unnumbered paragraph

" ~ interest or current cost whichever is higher. (ii) In case where allottees of the localities mentioned (i) above default a small percentage of demand amount upto 10% beyond the due date, this delay, if regularised would be on "Old interest." (iii) In other cases of all category flats i.e. where the construction of flats has been undertaken by other zones ofEngineering the restoration shall be at "Old Cost-interest". 2. A decision exists that while working out the current cost for in South Delhi, a surcharge of20% from the price worked per old formula, will be added. This surcharge will continue added for South Delhi flats. The interest rates in the above shall be@ 18% per annum on the default amount. C. RESTORATION CHARGES: In addition to the above, the allottees/allocatees whose allotment is restored by the competent authority, shall be liable to Restoration Charges @ 2.5% of the registration money of respective scheme."

pp. 826–827, margin E

Unnumbered paragraph

15. Another office order dated 31.3 .1999 was issued in regard imposition of 20% surcharge over and above disposal price only respect of registrants in South Delhi, relevant portion whereof reads under:

p. 827, margin D

Unnumbered paragraph

"2. Price of the flat (i) In cases (pertaining to any locality) where demanded amounts were received prior to 22.08.1996 by DDA, the restoration of allotment/regularisation of delay, if consider~d would

p. 827, margin E

Unnumbered paragraph

"old cost interest". (ii) In case where allottees default a small percentage of demanded amount upto 10% beyond the due date, the

p. 827, margin F

Unnumbered paragraph

if regularised, would be on "old cost+ interest". (lii) If the allocated/allotted flat is in South Delhi i.e. where construction has been undertaken by the South East Zone South West Zone of the Engineering Wing except Dwarka (being in West Delhi), the price of the flat, if restored, would be "old cost+ interest or current cost", whichever is higher. A This clause will be applicable in cases for which demanded amount by DDA is received after 22.08.1996 and the delay

pp. 827–828, margin F

Unnumbered paragraph

is regularised. (iv) In other cases of all category flats i.e. where the construction

p. 828

Unnumbered paragraph

of flats has been undertaken by other zones of Engineering B Wing, the restoration shall be at "old cost+ interest".

p. 828

Unnumbered paragraph

3. Sur Charge

p. 828

Unnumbered paragraph

The premium of20% over the disposal cost worked out on

p. 828

Unnumbered paragraph

current cost or old cost for the SFS flats in South Delhi, where the real value in the market ofDDA flats is much more than DDA is charging as per its costing formula, shall be charged."

p. 828

Unnumbered paragraph

16. The said orders were issued in purported supersession of the

p. 828, margin C

Unnumbered paragraph

previous orders on the subject and were to come into force with immediate effect. Some of the registrants made payments pursuant thereto or in furtherance thereof. Some had made payments although, according to them, aforementioned resolution will have no application to their case.

p. 828, margin C

Unnumbered paragraph

17. The said resolution was given a retrospective effect and retroactive operation.

p. 828, margin D

Unnumbered paragraph

Proceedings :

p. 828, margin D

Unnumbered paragraph

18. Several writ petitions were filed at that stage questioning the

p. 828, margin D

Unnumbered paragraph

legality and/or validity of the said purported resolutions.

p. 828, margin D

Unnumbered paragraph

19. A learned Single Judge of the Delhi High Court allowed the said ~ writ petitions in part quashing the policy of charging current cost and upholding the policy of charging 20% surcharge. Letters Patent Appeals were preferred thereagainst. A Division Bench of the High Court, having

p. 828, margin F

Unnumbered paragraph

regard to conflict in decisions operating in the field referred the matter to a larger Bench.

p. 828, margin F

Unnumbered paragraph

20·. The Full Bench of the said Court by reason of the impugned judgment modified the judgment and order of the learned Single Judge in respect of 'current cost' holding that the Authority had the requisite

p. 828, margin G

Unnumbered paragraph

jurisdiction also in respect thereof. The validity oflevy of20% surcharge was also upheld.

p. 828, margin G

Unnumbered paragraph

before the Full Bench :

p. 829, margin A

Unnumbered paragraph

21. Before the Full Bench, the registrants, inter alia,

p. 829, margin A

Unnumbered paragraph

levy of an additional amount over and above the allocatees or flats in South Delhi was wholly unjustified.

p. 829, margin A

Unnumbered paragraph

that adoption of current cost formula being contrary was also not sustainable in law inasmuch as rights

p. 829, margin A

Unnumbered paragraph

crystalliz.ed on issuance of the allocation letter and allotment of flat took place. Levy of surcharge amounts

p. 829, margin B

Unnumbered paragraph

cess, wherefor there is no authority in law.

p. 829, margin A

Unnumbered paragraph

22. Relying on or on the basis of a decision of this Court and Ors. v. Delhi Development Authority, AIR

p. 829, margin C

Unnumbered paragraph

on Delhi Development Authority v. Pushpendra AIR (1995) SC 1, the respondents, on the other the right of registrants gets crystallized only

p. 829, margin C

Unnumbered paragraph

at the stage of issuance of allocation letter. upon a Full Bench decision of the High Court Delhi Development Authority, (1995) 1 AD (Delhi)

p. 829, margin C

Unnumbered paragraph

delve into the price fixation policy was also questioned. Issues raised before the Full Bench :

p. 829, margin D

Unnumbered paragraph

23. Two principal issues which were raised before the High

p. 829, margin E

Unnumbered paragraph

the action of the Development Authority in surcharge from the registrants of the South Delhi Whether demand for payment of current cost as calculated Development Authority from the defaulter said to be justified?"

p. 829, margin E

Unnumbered paragraph

the Full Bench : 24.

p. 829, margin G

Unnumbered paragraph

of 20% surcharge is within the competence Authority in view of the definition of the 'disposal price' A contained in Regulation 2(13) of the Delhi Development Authority (Management and Disposal of Housing Estates) Regulations, 1968 (for short, 'the Regulations'), in respect whereof a decision was taken by the Vice-Chairman on

pp. 829–830, margin G

Unnumbered paragraph

22.08.1996. (ii) The said Regulations governing the field exclusively permits the Authority to decide and fix the price which would include surcharge being in the realm of contract, the relationship between the parties was clearly contractual; surcharge being

p. 830

Unnumbered paragraph

a component of the price of the flat. (iii) It is also to be noted that most of the Appellants were defaulter who had defaulted in making payments of the first four instalments on time and therefore there was delay in making payments in their cases. Since there was an automatic cancellation clause in the agreement the original contracts stood

p. 830, margin B

Unnumbered paragraph

cancelled. (iv) Regulation 2(13) of the DDA Regulations defined disposal price or hire purchase price in relation to a property to mean

p. 830, margin B

Unnumbered paragraph

such price as may be fixed by the authority. Hence the levy of surcharge was within the competence of the authority.

p. 830, margin B

Unnumbered paragraph

(v) DOA could include surcharge in its pricing formula which would be in the realm of contract as the relationship was purely

p. 830, margin E

Unnumbered paragraph

contractual. (vi) The meaning of the word "cost and price" has been settled by the Full Bench of the Delhi High Court in Sheelawant v. ODA which was upheld by the Supreme Court and reaffirmed

p. 830, margin E

Unnumbered paragraph

in DDA v. Ashok Kumar Behl [2002] 7 SCC 1352. (vii) The present case was different from the case of P.N Verma

p. 830, margin F

Unnumbered paragraph

v. Union of India, AIR (1985) (Delhi) 417] Submissions of the learned counsel on behalf of the registrants: 25. Mr. Rungta, Mr. Maninder Singh and Mr. Shekhar, learned counsel, submitted : A (i) Having regard to the admitted fact that all allocations were made during the period 1991 and 1994 and all of them having paid the instalments except the fourth one, prior to taking of the purported policy decision dated 22.08.1996, the Authority had no jurisdiction either to recalculate the current cost or

pp. 830–831, margin F

Unnumbered paragraph

impose a levy of20% surcharge . (ii) As the impugned 'Levy' comprises of three elements, namely, (i) the current cost which is determined; whereover (ii) 20% over the actual cost is taken into consideration, and again (iii) 20% surcharge is required to be paid, the same is

p. 831

Unnumbered paragraph

unreasonable. (iii) The Full Bench wrongly applied P.N Verma (supra), R.K Sacher (supra) and Premji Bhai Parmar (supra), which were decided on wholly different set of facts as the scheme(s) D involved therein was for low income group of people in terms whereof payments were to be made on completion of construction; whereas in the case of SFS, instalments of

p. 831

Unnumbered paragraph

payment is sought for immediately after the allocation. (iv) Restoration of allotment in the case of defaulter having been E the subject-matter of contract, the terms and conditions thereof could not have been altered or modified by the Authority

p. 831

Unnumbered paragraph

unilaterally. 4.4 (v) In any event, the impugned policy decision can not be given

p. 831

Unnumbered paragraph

retrospective effect or retrospective operation. (vi) Classification for value of flats being income-wise, area-wise, time-wise and scheme-wise as has been laid down in Premji Bhai Parmar (supra), any micro classification introduced by the impugned policy decision insofar as the registrants of South Delhi alone had been. asked to pay a higher amount must be

p. 831

Unnumbered paragraph

held to be discriminatory in nature. (vii) The purported cut-off date being 22.08.1996 creates a class between those whose allotments, although cancelled, had been restored on the terms of the contract and those who had

pp. 831–832

Unnumbered paragraph

applied for restoration thereafter. (viii) As policy did not prescribe any rational basis and the same having wrongly been applied, the same is wholly without

p. 832

Unnumbered paragraph

jurisdiction and, thus, a nullity. (ix) Clause 5 .10 of the brochure has wrongly been applied by the Full Bench insofar as value of the land and cost of construction were also existing in P.N Verma (supra), R.K .

p. 832

Unnumbered paragraph

Sacher (supra) and Premji Bhai Parmar (supra). (x) The policy decision having been taken on the basis of 'lack of cash flow', the stand taken by the Authority in its counter affidavit, that a large sum of money was invested for rehabilitation of the migrants from Jarnmu & Kashmir and

p. 832

Unnumbered paragraph

Punjab is wholly untenable. (xi) As the current cost of the flat was required to be determined in terms of the definition contained in Regulation 2(13) of the Regulation, any other mode or method adopted in respect

p. 832

Unnumbered paragraph

thereof was wholly illegal. (xii) Had such value been required to be arrived at having regard to the nature and time of the project when it was launched, the impugned policy decision is barred under the principle of

p. 832, margin D

Unnumbered paragraph

promissory estoppel. (xiii) By reason of an Executive Order, levy cannot be imposed

p. 832, margin D

Unnumbered paragraph

with retrospective effect. t- > (xiv) The Full Bench of the High Court misconstrued and misinterpreted the decision of the Division Bench of the Delhi High Court in P.N Verma (supra), which covered the case

p. 832, margin D

Unnumbered paragraph

of registrants.

p. 832, margin F

Unnumbered paragraph

26. Mr. Arun Jaitley and Mr. Sunil Gupta, learned senior counsel, appearing on behalf of the respondents, on the other hand, submitted :

p. 832, margin F

Unnumbered paragraph

(i) The relationship between the parties being contractual, the writ petitions were not maintainable. (ii) Price fixation of flats being within the exclusive domain of the Authority, the High Court has rightly refused to interfere

pp. 832–833, margin F

Unnumbered paragraph

therewith. (iii) The findings arrived at in P.N Verma (supra) falling in the line of Pushpendra Kumar Jain (supra), on the one hand, and Premji Bhai Parmar (supra), on the other, are strictly not applicable in this case as the policy decision adopted by the Authority on 22.08.1996 was a new one in terms whereof having regard to the equitable principle in mind, the Authority

p. 833, margin A

Unnumbered paragraph

adopted a policy de'hors clause ( 4) of the letter of allotment. (iv) This Court not only in Premji Bhai Parmar (supra) but also subsequently having upheld the decisions of the Delhi High Court in P.N Verma (supra) and Sheelawanti (supra) and in D.D.A. v. Ashok Kumar Behl [2002] 7 SCC 135], the same

p. 833, margin B

Unnumbered paragraph

constituted a binding precedent. (v) Sections 5 and 6 of the Act read with Regulation 5 having authorised the Authority to fix the price of the flats, the validity of impugned restoration policy comprising payment of surcharge of 20% and the interest on the said rate or current cost whichever is higher, could not have been questioned in

p. 833, margin C

Unnumbered paragraph

writ proceedings. (vi) As the policy was formulated on the representations made by the registrants, the registrants are estopped and precluded from

p. 833, margin E

Unnumbered paragraph

questioning the validity of the same. (vii) In a case of this nature where interpretation of clause of

p. 833, margin E

Unnumbered paragraph

contract is involved, judicial review is not permissible. (viii) Levy of surcharge for the subsidised schemes for weaker sections of the society having, inter alia, been upheld in Premji Bhai Parmar (supra), the impugned policy decision must be held to be reasonable so as to satisfy the tests of Article 14

p. 833, margin F

Unnumbered paragraph

of the Constitution oflndia. (ix) Cost of the land even in South Delhi having been worked out on the valuation of the land situated in Dwarka, classification A made in respect of the allocation at South Delhi where market rates were much higher from the actual cost, the scheme for restoration of flats in that area cannot be held to be arbitrary

pp. 833–834, margin G

Unnumbered paragraph

or discriminatory. Statutory provisions :

p. 834

Unnumbered paragraph

27. The Act was enacted to provide for the development of Delhi according to plan and for matters connected therewith or ancillary thereto.

p. 834

Unnumbered paragraph

Interpretation clause is contained in Section 2 of the Act. Section 2(h) defines the term 'Regulation' to mean a Regulation made under this Act.

p. 834

Unnumbered paragraph

Section 3 provides for constitution of the Authority consisting of a Chairman, who shall be the Lieutenant Governor of the National Capital

p. 834

Unnumbered paragraph

...

p. 834

Unnumbered paragraph

Territory of Delhi, ex-officio, a Vice-Chairman to be appointed by the D Central Government, amongst others. Section 4 provides for staff of the Authority. Section 5-A provides for constitution of Committee in the following terms :

p. 834

Unnumbered paragraph

"5-A. Constitution ofCommittee.-(1) The Authority may constitute as many Committees consisting wholly of members or wholly of other persons or partly of members and partly of other persons and for such purpose or purposes as it may think fit.

p. 834

Unnumbered paragraph

(2) A Committee constituted under this Section shall meet at such time and place and shall observe such Rules of procedure in regard to the transaction of business at its meetings as may be determined by Regulations made in this behalf.

p. 834

Unnumbered paragraph

(3) The members of a Committee (other than the member~ of the Authority) shall be paid such fees and allowances for attetldipg

p. 834

Unnumbered paragraph

its meetings and for attending to any other work of the Authority, as may be determined by Regulations made in this behalf."

p. 834

Unnumbered paragraph

" ~ Section 6 provides for objects of the Authority, in the following terms: "6. Objects of the Authority.- The objects of the Authority shall be to promote and secure the development of Delhi according to plan and for that purpose the Authority shall have the power to A acquire, hold, manage and dispose ofland and other property, to carry out building, engineering, and manage and dispose of land and property, to execute works in connection with supply of water and electricity, disposal of sewage and other services and amenities and generally to do anything necessary or expedient for purposes B of such development for purposes incidental thereto :

pp. 834–835, margin G

Unnumbered paragraph

Provided that save as provided in this Act, nothing contained in this act shall be construed as authorizing the disregard by the Authority of any law for the time being in force." Section 52 of the Act reads as under: "52. Power to delegate .- (1) The Authority may, by notification in the Official Gazette, direct that any power exercisable by it under this Act except the power to make Regulations may also be exercised by such officer or local Authority or committee D constituted under Section 5-A as may be mentioned therein, in such cases and subject to such conditions, if any, as may be specified therein. (2) The Central Government may, by notification in the Official E Gazette, direct that any power exercisable by it under this Act, except the power to make Rules may also be exercised by such officer as may be mentioned therein, in such cases and subject to such conditions, if any, as may be specified therein. (3) The Lieutenant Governor of the National Capital Territory of F Delhi may, by notification in the Official Gazette, direct that any power exercisable by him under this Act, except the power to hear appeals, may also be exercised by such officer as may be mentioned therein, in such cases and subject to such conditions, if any, as may be specified therein." G Section 57 (l)(f) of the Act reads as under: "57. Power to make Regulations. (1) The Authority, with the previous approval of the Central Government, may, by notification A in the Official Gazette, make Regulations consistent with this Act and the Rules made thereunder, to carry out the purposes of this Act, and without prejudice to ·the generality of this power, such Regulations may provide for - .........

pp. 835–836

Unnumbered paragraph

(f) The terms and conditions subject to which user oflands and buildings in contravention of plans may be continued." ' ~

p. 836

Unnumbered paragraph

28. Indisputably, in exercise of its regulation making power contained in Section 57 of the Act, the Central Government made regulations kno\'.n as 'Delhi Development Authority (Management and Disposal of Housing Estates) Regulations, 1968'.

p. 836

Unnumbered paragraph

Regulation 2(13) thereof defines 'disposal price' in the following terms:

p. 836

Unnumbered paragraph

"2( 13) "disposal price" or "hire purchase price" in relation to property means such price as may be fixed by the Authority for such property."

p. 836

Unnumbered paragraph

Sub-sections (25) and (30) of Section 2 of the Act define "penalty" and "Scheme" respectively, as under:

p. 836

Unnumbered paragraph

"2(25) "penalty" means an additional amount as laid do"-TI in the relevant agreement payable by the allottee or hirer as a

p. 836, margin E

Unnumbered paragraph

consequence of his default in the payment of prescribed dues;" F "2(30) "scheme" means a scheme prepared by the Authority for the creation of one or more housing estates;"

p. 836, margin E

Unnumbered paragraph

Regulation 3 empowers the Vice-Chairman to administer the Act subject to general guidance and resolutions of the Authority, who may delegate his powers to any officer of the Authority. Regulation 5 provides for disposal of the property which may be effected by either hire-purchase or sale or in such other manner and subject to such terms and conditions as may be decided by the Authority from time to time.

p. 836, margin E

Unnumbered paragraph

Regulation 6 provides for fixation of price to be one which may be determined by the Authority.

p. 836, margin E

Unnumbered paragraph

Regulation 8 provides for the manner of payment of disposal price.

p. 837, margin A

Unnumbered paragraph

Chapter III of the Regulations provides for the procedure disposal of property. In terms of Regulation 30 of the Regulations, Authority is mandated to prepare an allotment register in which names and other particulars of the registrants are to be entered. The names the persons on the waiting list should also be entered in a separate section of the same register in the order in which their names appear in the of lots. Power to decide representations has been conferred upon Committee in regard to the selection of applicants for allotment of property.

p. 837, margin A

Unnumbered paragraph

Regulation 37 provides for handing over of possession of property.

p. 837, margin C

Unnumbered paragraph

Regulation 59 provides for delegation of all or any of the powers the authority under the Regulations to the Vice-Chairman or to a whole time member.

p. 837, margin C

Unnumbered paragraph

Functions of DDA :

p. 837, margin D

Unnumbered paragraph

29. In Premji Bhai Parmar (supra), a Bench'ofthis Court noticed that the Authority had adopted a resolution delegating its power to Vice-Chairman and the power to fix disposal price was said to have delegated to the Vice-Chairman.

p. 837, margin D

Unnumbered paragraph

30. At the outset, we may notice that the stand taken before us Mr. Jaitely that the scheme in question was a new one which had framed keeping in view the exigencies of the situation arising out of representations made by the registrants, whose allotment had cancelled, had not been raised before the High Court. Such a stand, fact, had never been taken.

p. 837, margin E

Unnumbered paragraph

31. The Authority issues an invitation through its brochure.

p. 837, margin F

Unnumbered paragraph

32. The 5th SFS Scheme was announced in the year 1982. r- person could himself get registered upon payment of fees prescribed therefor. The brochure published by the Authority indicated the tentative cost of different flats in different scheme category-wise. Pursuant thereto, an intending allocattee applies thereunder, and if in the draw of lots A declared successful, an allocation-cum-demand letter specifying the locality and the floor is communicated to him. It is not the case of the parties that the estimated cost or the tentative cost was the final one. The Authority indisputably has the jurisdiction to fix the disposal price finally upon taking

pp. 837–838, margin G

Unnumbered paragraph

into consideration all relevant factors. In terms of the Jetter of allotment the estimated price is to be paid in four equal instalments. Admittedly, question of the final cost is communicated to the registrants who is asked to pay the balance amount after deducting the payment made in four instalments together with the 5th instalment. The estimated cost, according

p. 838

Unnumbered paragraph

to the Authority, itself should be worked out having regard to the following parameters.

p. 838, margin B

Unnumbered paragraph

l. Cost of construction 2. Community facility charges

p. 838, margin C

Unnumbered paragraph

3. Floor equilization for ground floor and subsidised for upper floors 4. Departmental charges 5. Administrative charges

p. 838, margin C

Unnumbered paragraph

6. Cost of land (Land Rate on the date of allocation letter is taken).

p. 838, margin D

Unnumbered paragraph

The land rates of the project area are determined on the basis of break even rates arrived on cost benefit analysis which includes cost of acquisition, enhanced compensation and future realisations. This rate is approved by the Government oflndia. The land rates approved by the Government oflndia for Dwarka is also applied on flats in South Delhi. They are predetermined rates on actual break even basis. 7. Surcharge@20% w.e.f. 16.8.96."

p. 838, margin E

Unnumbered paragraph

33. Indisputably again, other components for determining the cost remains the same every year. The only change which was effected, is the change in the land rate, which is approved by the Government. Other

p. 838, margin E

Unnumbered paragraph

parameters for calculating the material cost were approved by the Vice- H Chairman of the Authority.

p. 838, margin E

Unnumbered paragraph

34. Delhi Development Authority has been created under a Parliamentary Act. It, indisputedly, is a State within the meaning of Article 12 of the Constitution of India. Being so, the provisions of Part III of the Constitution oflndia must be applied by it. Undisputedly, again, it has also the duty to strive hard for giving effect to the Directive Principles of State Policy as contained in Part IV of the Constitution oflndia.

p. 839

Unnumbered paragraph

35. Objects of the DDA is stated in Section 6 of the Act. We may notice that although the heading of Section 6 states about the object of the Act, the main provision contain both its objects and powers. It is also curious to notice that its power to constitute a scheme so as to provide housing facilities to the citizens of India and, in particular, those belonging to lower income group as also coming from lower strata of the society has not been mentioned which we would find pari materia in statutes framed by other States. [See Chairman, Indore Vikas Pradhikaran v. Mis. Pure Industrial Cock & Chem. Ltd. & Ors., (2007) 8 SCALE 110]

p. 839, margin B

Unnumbered paragraph

36. It is accepted that although the Act was enacted in the year 1957, the idea of providing for implementation of such housing scheme started much later. The Rules, as noticed hereinbefore, were framed only in the year 1968 and implementation of actual housing schemes are said to have been started in late seventies or early eighties.

p. 839, margin D

Unnumbered paragraph

37. While acting as a 'State' within the meaning of Article 12 of the Constitution oflndia, it is imperative that DD.A., while inlplementing its statutory power, upholds the fundamental rights of the citizens and strive hard to give effect to their Directive Principles of the State Policy. We, however, cannot also shut our eyes to the fact that in terms of Article 37 of the Constitution of India whereas the provisions of Part III are justiciable, the provisions of Part IV are not. Only when an action of the State is taken to give effect to any of the provision of Part IV of the Constitution oflndia which is not otherwise ultra vires the Constitution or offends the principles embodied in Part III of the Constitution oflndia, the same may be upheld, having regard to the provisions contained in Part III thereof. The action of the State, therefore, must at the first instance ba ii.djudged on the touchstone of the principles of Fundamental Rights and then the provisions contained in the Parliamentary Act, the regulations A framed thereunder as also the terms of the contract entered into by and between the parties.

pp. 839–840, margin E

Unnumbered paragraph

38. We may or may not agree with the submission of learned counsel for the appellants that the right of housing arising out of such a scheme is

p. 840

Unnumbered paragraph

a fundamental right within the meaning of Articles 19(l)(e) and 21 of the B Constitution of India, but there cannot be any doubt whatsoever that the action of a State must satisfy the principal requirements of Article 14, viz., treating persons similarly situated equally and grant of equal protection to them. Reasonableness and fairness is the heart and soul of Article 14 of

p. 840

Unnumbered paragraph

the Constitution of India. Keeping the aforementioned principles in mind, we may consider the points involved herein.

p. 840

Unnumbered paragraph

Scheme

p. 840, margin C

Unnumbered paragraph

39. The basic fact that the scheme was floated in the year 1991 being

p. 840, margin C

Unnumbered paragraph

SFS is not in dispute. It has also not been denied or disputed before us that the said scheme in its application is fundamentally different from those of the others schemes, viz., MIG, LIG, Janta and Expandable Housing Scheme. There is also not much dispute as regards the fact that in terms of the said scheme, estimated costs as well as rights and liabilities of the

p. 840, margin C

Unnumbered paragraph

parties are laid down in the invitation to offer. Allocation of the area, floor etc. ought to be notified on acceptance of the offer by the registrants.

p. 840, margin D

Unnumbered paragraph

Such allocation again undisputedly is made on the basis of draw oflot having regard to the specific number of flats available. The registrants have no choice in that behalf. Although he might have exercised his right of

p. 840, margin E

Unnumbered paragraph

option in relation to the area or the floor but then he, in fact, has no hands thereover. The letter of allotment contains the schedule of payment as also other terms and conditions in support thereof.

p. 840, margin E

Unnumbered paragraph

40. We, in this batch of appeals, are principally concerned, inter

p. 840, margin F

Unnumbered paragraph

alia, with the interpretation of clause 4 of the Letters of Allotment.

p. 840, margin F

Unnumbered paragraph

41. This scheme, ordinarily, was to operate within a time frame. DDA was expected to complete the constructions within a period of2Yi years. Four six-monthly instalments were required to be paid by the registrants ·within the aforementioned period which would include, the gr!ice period.

p. 840, margin G

Unnumbered paragraph

42. Whereas ninety days' time is not taken into consideration for purpose of computing the default clause, indisputably, again the power

pp. 840–841, margin G

Unnumbered paragraph

authority to regularize the default on receipt of interest@ 18% per annum on the amount due to and owing to an allottee is specifically

p. 841, margin A

Unnumbered paragraph

for. The period of2Yz years vis-a-vis the six-monthly interest have been laid down keeping in view the fact that whereas the

p. 841, margin A

Unnumbered paragraph

deposited by the registrants by instalments would be invested for construction of the flats. 18% interest is prescribed for default both on of the DDA as also on the part of the registrants. No time limit

p. 841, margin A

Unnumbered paragraph

for completion of the scheme. The only penalty which the scheme prescribes is payment of interest. So far as area of SFS is concerned, a registrant has no role to play. Admittedly, constructions have been completed in the year 2000.

p. 841, margin B

Unnumbered paragraph

43. For interpretation of clause 4 of the scheme, the aforementioned background is required to be borne in mind.

p. 841, margin C

Unnumbered paragraph

Ingredients of clause 4 are : "(a) The allotment letter would indicate the four due dates on which the first four installments are to be paid. The fifth installment would be paid on demand. 90 days delay in the first four instalL111ents is condonable subject to payment of prescribed interest. After the expiry of 90 days if payment is not made for first four installments there would be automatic cancellation. This automatic cancellation can be restored on payment of interest and other charges subject to availability of the flat. The cancellation due to non-payment of final installment will be made ifthe payment is not made within 120 days with no

p. 841, margin C

Unnumbered paragraph

provision of any further extension."

p. 841, margin F

Unnumbered paragraph

44. It has not been denied or disputed that although the registrants

p. 841, margin G

Unnumbered paragraph

in making payments but the flats were available. In fact, when default took place, the flats were not constructed. They have, thus, been allotted to the persons on the wait list. 45. It may be true that recourse to clause (d) should be undertaken A by the a!locattees within a reasonable time. What would be a reasonable time would, however, depend on the facts and circumstances of each case. No hard and fast mle can be laid down therefor.

pp. 841–842, margin G

Unnumbered paragraph

46. In a given case, it may be a few months but in another having

p. 842

Unnumbered paragraph

regard to the conduct ofDDA, it may be one year or more. What would constitute a reasonable period must also be considered keeping in view the rights of the parties as also the fact that in terms of clause 4 of the offer of allotment there does not exist any prohibition to pray for regularization upon default, even after a period of 120 days. In a situation

p. 842

Unnumbered paragraph

of this nature, it may not be unjustified to arrive at the conclusion that such a right can be exercised, if not, when the flats were ready for handing over actual possession, but at least when there has been a substantial progress. We must also take into consideration that the scheme, the letter of allotment, the contract between the parties to pay interest in case of

p. 842, margin B

Unnumbered paragraph

default to each other leads to a conclusion that DDA in its wisdom thought that payment of 18% interest shall subserve the purpose. We, however, hasten to add that it does not mean that DDA must entertain such an application for restoration and/or condonation of default despite lapse of time. It has its own right in relation thereto which may be invoked. The

p. 842, margin C

Unnumbered paragraph

right to allot the flat to a person who is on the wait-list as a result whereof a seal of finality can be put, the right of the registrants or registrants even the whole or a part of the advance or other amounts deposited by him stand forfeited.

p. 842, margin D

Unnumbered paragraph

Interpretation of the Act :

p. 842, margin E

Unnumbered paragraph

47. DDA functions through the Committees constituted in terms of Section 5A of the Act. Power has been delegated in favour of its Chairman and the Vice-Chairman. Such delegation of power, however, as provided for under Section 52 of the Act does not extend to make

p. 842, margin F

Unnumbered paragraph

regulations. What, therefore, cannot be done by way of regulation, cannot be done by executive order.

p. 842, margin F

Unnumbered paragraph

48. It has not been denied or disputed that having regard to clause 5 .10 of the brochure and clause 4 of the letter of allotment, the term "tentative cost" must be given its natural meaning.

p. 842, margin G

Unnumbered paragraph

49. It varies from time to time as it is not a one time process. The A ...

p. 843

Unnumbered paragraph

price difference between the estimated cost and the initial cost "as it worked out on the completion as per costing formula in vogue" would have to be paid along with the 5th and final instalment.

p. 843

Unnumbered paragraph

Notifications :

p. 843

Unnumbered paragraph

50. The impugned circulars have three distinct elements : ~· 1. Price of South Delhi flats would be worked out by adding 20% surcharge in terms of the office order dated 16.8.1996 duly

p. 843

Unnumbered paragraph

approved on 22.8.1996.

p. 843

Unnumbered paragraph

2. 20% surcharge will have to be paid in case where there is a

p. 843

Unnumbered paragraph

small delay, in which case only interest has to be paid.

p. 843

Unnumbered paragraph

3. In all other cases original cost + 18% or the current cost

p. 843

Unnumbered paragraph

whichever is higher would be payable.

p. 843

Unnumbered paragraph

51. Legality and/or validity of the said circulars is in question. We may, at the outset, notice that there is nothing on record to show that the Office Orders dated 16.8.1996, 27.8.1996 and 21.3.1999 were published in the Gazette or were otherwise brought to the notice of the registrants.

p. 843

Unnumbered paragraph

Conduct: E

p. 843

Unnumbered paragraph

52. Conduct of the parties may be noticed from the case ofManjit Singh. Admittedly, the registrants failed to pay instalments within the stipulated period. A notice dated 23.4.1997 was served on him which is in the following terms :

p. 843

Unnumbered paragraph

"WHEREAS you had been allocated a second floor category - II, SFS flat in Pkt. F, Sheikh Saria Residential Scheme vide allocation - cum demand letter dated 31.3.93 under the DDA (Management & Disposal of Housing Estates) Regulations 1968

p. 843

Unnumbered paragraph

against your registration under the 5th SFS - 1982. 1- AND WHEREAS as per the allocation cum demand letter the following installments were to be paid as per the following schedule:- A Installments Amount Due Date Installment Challan

pp. 843–844

Unnumbered paragraph

paid on No. I.st Rs.1,35,867/- 30.4.93 24.5.93 032601

p. 844

Unnumbered paragraph

(Rs.1,35,867) Ilnd Rs.1,25,060/- 30.10.93 30.10.93 112025 31.05.94 (Rs.43,675)

p. 844

Unnumbered paragraph

(Rs.50,000) III rd Rs.1,56,325/- 30.4.94 24.11.94 010243

p. 844

Unnumbered paragraph

(Rs.50,000) c IV th Rs.1,25,060 30.10.96 25.07.96 010245

p. 844

Unnumbered paragraph

(Rs.50,000)

p. 844

Unnumbered paragraph

From the perusal of the above chart, it can be seen that you have not deposited the installment as per schedule indicated in the allocation cum demand letter.

p. 844

Unnumbered paragraph

AND WHEREAS as per the terms and conditions of the allocation cum demand letter as contained in Clause - 4 the allocation was liable to be cancelled if the installments are not made as per the schedule.

p. 844

Unnumbered paragraph

AND WHEREAS it is evident that you failed to deposit the installments as per the schedule and thus have committed the breach of the terms and conditions of the allocation cum demand letter dated 31.3 .1993

p. 844

Unnumbered paragraph

~-, F Therefore, I, Dy. Director (SFS) hereby inform you that the allocation made to you vide letter dated 26.3 .93 - 31.3 .1993 " stands automatically cancelled due to the breach of the terms and conditions of allocation.

p. 844

Unnumbered paragraph

It is further inform (sic) that the 5th SFS Scheme 1982 stands already closed, therefore, you are advised to return all the original FDR, Demand cum allocation letter and third copy of challan so ~ that your case can be processed for the refund of the amount deposited by you."

p. 844

Unnumbered paragraph

53. He submitted a representation praying for condonation of default. A In his representation, he stated:

p. 845

Unnumbered paragraph

"Immediately on receipt of the DDA letter I ran hither and thither for financial loans from relatives, friends, and well wishes and was able to deposit Rs.2,12,770/- vide challan No.039576 dated - 12.5.97 (Annexure F) bringing the total payment to DDA to 90% of the cost of flat. The flats are yet to be completed. I now, therefore, humbly APPEAL to you to condone the delay in the payment of installments for reasons stated above, on humanitarian and compassionate grounds and to regularise the allocation of the flat for which act of kindness I shall ever pray. I am also ready to pay any amount yet due in the form ofinterest."

p. 845

Unnumbered paragraph

54. The said representation was accepted by DDA in terms of a letter dated 10.12.1998 which reads as under :

p. 845

Unnumbered paragraph

"It is our pleasure to inform that you have been allotted SFS Flat with the following details through a computerized draw held on _j 10/1998:- Flat No. 61 Floor SEC E Category II Sector Block Pocket Type F Locality SHEIKH SARAI

p. 845

Unnumbered paragraph

We are advising the Housing Acts Department to issue the 5th and Final Demand Letter to you at the earli\:st."

p. 845

Unnumbered paragraph

55. It allotted the flat. No condition therefor was put. It did not ask G for payment of any surcharge. The original terms were not deviated from . It did not ask for any extra-cost. The delay in payment of instalments was condoned and the allocation of flat which stood cancelled in terms of the aforementioned notice dated 23.4.1997 stood restored. DDA, thus, acted strictly in terms of the original scheme. The offer of the allocattee was H A accepted relying on or on the basis of clause 4, viz., the amount of default "

pp. 845–846

Unnumbered paragraph

and an interest charged thereupon@ 18% per annum. It is only when the 5th and final instalment was directed to be paid in tenns of demand letter dated 15.2.1999, the current cost computed in tenns of the office

p. 846

Unnumbered paragraph

order dated 16.8.1996 and subsequent office orders was included. The allocattee at that stage might not have any other option but to pay the same for obtaining possession. But by reason thereof, he never gave up his right to question the action on the part of DDA. Rule of estoppel, "therefore, has no application.

p. 846

Unnumbered paragraph

56. It was, on the other hand, DDA who having accepted the offer of the allocattee by restoring the allotment, in our opinion, is estopped and precluded from raising a plea as regards application of office order dated 16.8.1996. It may be noticed that even contents of those letters were not disclosed to the allocattee.

p. 846, margin B

Unnumbered paragraph

Was it a Restoration Scheme ?

p. 846, margin C

Unnumbered paragraph

57. The office orders, on the basis whereof the purported impugned policy had been taken, do not refer to the scheme as a restoration scheme. The resolutions do not say so. Had it been so, DDA would have issued

p. 846, margin C

Unnumbered paragraph

a fresh notification or at least made its stand clear to the allocattees either by way of public notice or by informing each of such defaulters individually.

p. 846, margin C

Unnumbered paragraph

Had such conditions for the purpose of restoration being made known, the allocattees would have accepted it or rejected it. Evidently, it is a part of the original scheme. It is not a new one. It is well known principle of

p. 846, margin E

Unnumbered paragraph

law that a person would be bound by the tenns of the contract subject of course to its validity. A contract in certain situations may also be avoided. With a view to make novation of a contract binding and in particular some of the tenns and conditions thereof, the offeree must be made known thereabout. A party to the contract cannot at a later stage,

p. 846, margin E

Unnumbered paragraph

while the contract was being perfonned, impose tenns and conditions which were not part of the offer and which were based upon unilateral issuance of office orders, but not communicated to the other party to the contract and which were not even the subject matter of a public notice. Apart from the fact that the parties rightly or wrongly proceeded on the basis that the demand by way of 5th instalment was a part of the original scheme, DDA in its counter affidavit either before the High Court or before A us did not raise any contra plea. Submissions of Mr. Jaitley in this behalf could have been taken into consideration only if they were pleaded in the counter affidavit filed by DDA before the High Court.

pp. 846–847, margin F

Unnumbered paragraph

58. We have also reservations that in absence of any provision contained in the Act or the Regulations, the delegatee on its own could frame such a new scheme. If not, the purported restoration policy would be ultra vires. We, therefore, cannot persuade ourselves to agree with the contention ofDDA that the restoration policy cannot be tested on grounds of terms and conditions of the original scheme. If it is a new scheme, it would bear repetition to state, the terms contained therein c should have been known to the allocattees. We, thus, have no other option but to proceed to consider the legality and/or validity of such imposition on the premise that the impugned policy decision is a part of the original scheme and does not contain any new policy.

p. 847

Unnumbered paragraph

Policy Decision :

p. 847

Unnumbered paragraph

59. An executive order termed as a policy decision is not beyond the pale of judicial review. Whereas the superior courts may not interfere with the nitty gritties of the policy, or substitute one by the other but it will not be correct to contend that the court shall like its judicial hands E off, when a plea is raised that the impugned decision is a policy decision. Interference therewith on the part of the superior court would not be without jurisdiction as it is subject to judicial review.

p. 847

Unnumbered paragraph

60. Broadly, a policy decision is subject to judicial review on the following grounds :

p. 847

Unnumbered paragraph

(a) if it is lll1constitutional; (b) ifit is de'hors the provisions of the Act and the Regulations; (c) if the delegatee has acted beyond its power of delegation; (d) ifthe executive policy is contrary to the statutory or a larger

p. 847

Unnumbered paragraph

policy .

p. 847

Unnumbered paragraph

61. The stand taken by DDA itself is that the relationship between the parties arises out of the contract. The terms and conditions therefor H A were, therefore, required to be complied with by both the parties. Tenns ~ and conditions of the contract can indisputably be altered or modified. They cannot, however, be done unilaterally unless there exists any provision either in contract itself or in law. Novation of contract in tenns

pp. 847–848

Unnumbered paragraph

of Section 60 of the Contract Act must precede the contract making process. The parties thereto must be ad idem so far as the tenns and conditions are concerned. IfDDA, a contracting party, intended to alter or modify the tenns of contract, it was obligatory on its part to bring the same to the notice of the allocate. Having not done so, it, relying on or

p. 848

Unnumbered paragraph

on the basis of the purported office orders which is not backed by any statute, new tenns of contract could thrust upon the other party to the contract. The said purported policy is, therefore, not beyond the pale of judicial review. In fact, being in the realm of contract, it cannot be stated to be a policy decision as such.

p. 848, margin B

Unnumbered paragraph

Price Fixation

p. 848, margin C

Unnumbered paragraph

62. We would assume that the office orders were issued by DDA keeping in view the representations made by a large number of defaulters. The plea taken by DDA gives rise to a dichotomy. If it is a case of contract qua contract, the provisions of the Contract Act must be taken

p. 848, margin C

Unnumbered paragraph

recourse to. IfDDA was exercising a statutory power, the same must be tested on application of doctrine of ultra vires. Floating a scheme for providing housing facilities to a group of people, although is governed by statute, power under the statute by an executive not only can be tested on the touchstone of Article 14 of the Constitution of India, but can also

p. 848, margin C

Unnumbered paragraph

be tested on the touchstone of source of the power under the statute. F No provision either in the Act or the Regulations was brought to our notice which makes the allocattee bound by the purported policy decision taken by DDA. Even if it is so, the superior courts may exercise its power of judicial review as the power which is sought to be exercised by a statutory

p. 848, margin E

Unnumbered paragraph

authority is not under the contract but under a statute. When a contract emanates from a statute or is otherwise governed by the provisions thereof, the superior court can also exercise the power of judicial review.

p. 848, margin E

Unnumbered paragraph

63. In Gujarat State Financial Corporation v. Mis. Lotus Hotels

p. 848, margin G

Unnumbered paragraph

Pvt. Ltd., [1983] 3 SCC 379: AIR (1983) SC 848], it is stated that such contracts can be subject to judicial review.

p. 848, margin G

Unnumbered paragraph

64. Regulations 5 and 6 should not be very liberally construed. A Concededly, the manner in which power is to be exercised is governed by the past practice. Norms have been fixed for computing the disposal cost. Although, the superior courts ordinarily would not interfere in the price fixation but there does not exist any absolute ban. In a case where fixation of price is required to be made in a particular manner and upon taking into consideration the factors prescribed and if price is fixed de' hors the statutory provisions, judicial review would be permissible.

p. 849

Unnumbered paragraph

65. Strong reliance has been placed upon the residuary power conferred upon the Authority to determine the cost of construction.

p. 849

Unnumbered paragraph

66. When the same is done having regard to the relevant factors on

p. 849

Unnumbered paragraph

the basis of which brochure as well as the notice inviting tender was issued, .......

p. 849

Unnumbered paragraph

the superior courts may not interfere; but the same must be done in terms of the original contract and not de' hors the same. The authority, even while exercising its residuary power, is required to act within the four comers of the contract. While doing so, the terms of the contract cannot be altered to include any other factors which were contemplated thereunder. While computing the extra cost, no additional factor, thus, can be taken into consideration. If such a power is conceded in the authority, the same would give rise to exercise of arbitrary power. It is not contemplated in law. When construing a provision delegates a power on an authority under a statute, the constitutional provisions must be kept in

p. 849

Unnumbered paragraph

mind _. 67. At the time of calculation of the amount which would be the subject matter of demand of 5th and final instalment, the jurisdiction of F DDA is to keep itself confined only to the factors on the basis whereof, the brochure has been issued and offer was made. No additional factor, thus, could be taken into consideration at the time of issuing notice other than the ones on the basis whereof offer was made by the registrants.

p. 849

Unnumbered paragraph

Imposition of equalization charge also falls within the said purview. G "' 68. There may be some charges like conversion charges which per se may or may not be bad. Conversion charges levied by the DDA pursuant to the directions issued by the Central Government which in tenns of Section 41 of the Act is binding on DDA for converting the leasehold A into freehold. However, such a power also must be exercised reasonably and fairly. Conversion of the property from leasehold to freehold is a separate transaction. The same has nothing to do with the actions, qua contract. Imposition of conversion charges, therefore, even if, per se, may

pp. 849–850

Unnumbered paragraph

not be held to be bad, the said factor cannot be taken into consideration for the purpose of computing construction costs. The High Court has struck down the inclusion of such conversion charges in the costing of the flats. After 1996, the ordinary cost of construction of a flat was Rs.2,00,000/-, in South Delhi but not only it framed the basis for

p. 850

Unnumbered paragraph

computing the final cost but also 20% additional amount as also 20% surcharge were claimed thereupon. Sometimes interest also was charged as and when applicable. Thus, so long the conversion charge is charged by way of a separate transaction, no exception can be taken. But, purpo1ted price fixation as has been done in the instant case cannot receive

p. 850, margin B

Unnumbered paragraph

our approval. The same is, thus, in our opinion, bad in law. D Applicability :

p. 850, margin C

Unnumbered paragraph

69. The scheme in question was floated in 1992-93. The purported default on the part of the registrants took place prior to the purported

p. 850, margin C

Unnumbered paragraph

adoption of the policy decision. The purported office order dated 16.8.1996 discloses shows that an internal decision had been taken to condone the delay in making payments of first four instalments. The authorities mentioned therein had been delegated with the power for the period(s) mentioned as under:

p. 850, margin C

Unnumbered paragraph

Director (H)-1 Upto 3 months Commissioner (Housing) Upto 1 year Principal Commissioner From 1 year to 1 Yz year

p. 850, margin E

Unnumbered paragraph

Vice-Chairman Full powers G Clause 3 of the said office order reads as under:

p. 850, margin E

Unnumbered paragraph

"There are presently cases in the Housing Department where there have been delays in the making of the payments of the flats allocated/allotted in South Delhi under SFS. Before the aforesaid revision took place, delays of one year or so were being regularized with usual charges, i.e., on payment of 18% interest per and restoration charges, etc. in few cases where delays unusually long, current price has also been demanded."

pp. 850–851, margin E

Unnumbered paragraph

70. Thus, a decision in that behalf had not only been taken was made applicable both in the case where the delay is of one so and the delay which was unusually long. By reason of the said circular, delay in making payments of instalment was to be condoned on payment of either current price or old price whichever is higher. From a perusal the Resolution dated 27 .8.1996, it appears that 20% surcharge was over the disposal cost worked out for the flats in South Delhi does not show that any subsidy was proposed to be granted migrants from Jammu and Kashmir or Punjab. The policy was taken with a view to balance the reduced cash in-flow. DDA, thus, had commercial aspect of the matter and not the social justice aspect.

p. 851, margin A

Unnumbered paragraph

71. Again, by reason of the office order dated 31.3 .1999, delegation of power in favour of various authorities was redefined. Vice-Chairman could deal with delay or default even if it exceeds year and six months. 22.8.1996 was prescribed as the cut off date the purpose thereof. Price of the flat was to be calculated on the either current price or old price whichever is higher. It was sought applied irrespective of the extent of delay. On what basis 22.8.1996 taken to be the cut off date has not been disclosed. We would, however, assume that the said date was taken into consideration in view Resolution dated 27.8.1996.

p. 851, margin C

Unnumbered paragraph

72. An executive officer, in absence of any provision of a cannot apply his own decision with a retrospective effect. A delegatee bound to act within the four comers of the delegation and not the same.

p. 851, margin F

Unnumbered paragraph

73. Delegation of power in favour of an authority under a statute must also be tested in terms of the statutory provisions. No provision under the Act or the Regulations has been brought to our notice empowers the delegatee to alter the terms and conditions of the contract with retrospective effect. The purported policy decision must, therefore, be tested not only having regard to the provisions of the statute but A having regard to clause 4 of the offer.

pp. 851–852, margin F

Unnumbered paragraph

74. Current cost has been calculated upon computing 20% over and above the actual cost. A provision for surcharge had also been made in terms whereof a premium of 20% over the disposal cost was worked

p. 852

Unnumbered paragraph

out on current cost for the SFS flats in South Delhi. Imposition of surch<rrge is subject to the condition that the real value in the market of DDA flats would be much more than it had been charging as per the cost formula. Parameters of computation of disposal price have been laid down which we have noticed supra. The authority having itself adopted

p. 852

Unnumbered paragraph

a formula for computing the disposal cost, the same was binding upon the delegatees. A delegatee cannot take any action contrary to or inconsistent with the factors laid down for computation of disposal cost as defined in Section 2(30) of the Act. Regulations 5 and 6 do not authorize the delegatee to apply a formula which was not contemplated

p. 852, margin B

Unnumbered paragraph

by the Authority itself If an Executive Authority in absence of any statutory provision cannot apply a decision with retrospective effect, the same would be ultra vires.

p. 852, margin C

Unnumbered paragraph

75. In Vice Chancellor, MD. University, Rohtak v. Jahan Singh,

p. 852, margin D

Unnumbered paragraph

(2007) 4 SCALE 226, this Court observed: E 'The Act does not confer any power on the Executive Council to make a regulation with retrospective effect. The purported regulations, thus, could not have been given retrospective effect or retro-active operation as it is now well-settled that in absence

p. 852, margin D

Unnumbered paragraph

of any provision contained in the legislative Act, a delegatee cannot make a delegated legislation with retrospective effect."

p. 852, margin D

Unnumbered paragraph

[See also Ashok Lanka and Anr. v. Rishi Dixit and Ors., [2005] 5 sec 598]

p. 852, margin F

Unnumbered paragraph

76. A definite price is an essential element of binding agreement. A definite price although need not be stated in the contract but it must be worked out on some premise as was laid down in the contract. A contract cannot be uncertain. It must not be vague. Section 29 of the Indian Contract Act reads as under :

p. 852, margin F

Unnumbered paragraph

"Section 29 - Agreements void for uncertainty Agreements, the meaning of which is not certain, or capable of A being made certain, are void."

pp. 852–853, margin G

Unnumbered paragraph

77. A contract, therefore, must be construed so as to lead to a conclusion that the parties understood the meaning thereof The terms of agreement cannot be vague or indefinite. No mechanism has been provided for interpretation of the terms of the contract. When a contract has been worked out, a fresh liability cannot thrust upon a contracting party.

p. 853

Unnumbered paragraph

78. It is well settled that a definite price is an essential element of a binding agreement. Although a definite price need not be stated in the contract, but assertion thereof either expressly or impliedly is imperative. c Impugned Judgment :

p. 853

Unnumbered paragraph

79. The Full Bench of the Delhi High Court has placed strong reliance on P.N Verma (supra). One of the fundamental errors which has been committed by the Full Bench, with respect, is applying P.N Verma D (supra) without noticing the distinction between the provisions contained in the clauses of the Brochure in the present case and those obtaining therein. In the present case Clause 5.10 of the DDA Brochure stipulates that the price mentioned in the allocation letter is only the estimated price and it could be changed only on the basis of escalations in the price to E be determined by DDA on the completion of flats. lnP.N Verma (supra), however, the price was to be fixed on allotment of flats. It gives rise to a lot of difference in determining the issue.

p. 853

Unnumbered paragraph

In P.N Verma (supra), the High Court observed: "24 ... If the stand of the DDA is that the price they demand is only on the same formula as was announced and that the increased price demanded is only due to escalation in cost of construction and fluctuation in other cost factors, then the issue will only be whether the fixation of price is in accordance with the contract and that can be gone into, both by reason of principle and because it will involve complicated factual investigations, only in a suit. This is the alternative stand of the DDA which we will discuss later. But if the DDA says, whatever we may have said earlier, we can fix the price or any basis and that cannot be questioned at all because A it is a contractual matter, the argument is fallacious because this stand of the DDA means going behind the contract and revising the earlier fonnula of price fixation which means travelling back to the pre-contractual statutory stage ... " It was also stated: "46 ... That actual cost was tentatively fixed at a figure 'which was announced subject, however, to variations in cost factors. It is not open to the DDA to alter this basis for the determination of the

pp. 853–854

Unnumbered paragraph

disposal cost. So long as the DDA adheres to this basis in fixing the disposal cost, court will not interfere. It will not interfere even if there should be some mistakes or exaggerations in the calculation of the components of the figure arrived at, as that would be a matter for detennination after evidence and investigation in a suit.

p. 854

Unnumbered paragraph

Even if an item should be included in the cost components, about the inclusion of which as one of the cost factors there could be some doubt, the writ court may not interfere and may leave the parties to fight out their battle in a regular suit. But where the disposal cost is fixed on a basis totally different from that announced earlier or where the components taken into account cannot be described by any stretch of imagination as cost factors or where a component of the cost is shown to have been fixed arbitrarily and without any basis whatsoever, the Court has no option but to quash the detennination of the disposal cost so fixed and direct the DDA to undertake afresh a proper detennination thereof in accordance with the terms of the original contract or after excluding the items ur1warrantedly included therein or after re-detennining the value of any component on a proper and reasoned basis ... "

p. 854, margin C

Unnumbered paragraph

On legal principle, therefore, ratio of P.N Verma (supra) is not very different from what has been held herein.

p. 854, margin D

Unnumbered paragraph

80. Another fundamental error committed by the Full Bench was to approve para 29 of the judgment of the Division Bench of the Delhi High ~ Court in R.K. Sachar v. DDA (LPA No. 727 of 2002 decided on

p. 854, margin D

Unnumbered paragraph

15.12.2003) opining that this Court had already approved the contention of the DDA that it was entitled to recover such a charge in the light of the decision in Premji Bhai Parmar (supra). A

pp. 854–855, margin D

Unnumbered paragraph

81. The Full Bench failed to notice that in P.N. Verma (supra) surcharge over and above the disposal price titled "equalization charge" purporting to provide subsidy for construction of flats for weaker sections of the society in trans Y arnuna area was held to be ultra vires and that

p. 855

Unnumbered paragraph

the said decision has been approved by this Court. P.N. Verma (supra),

p. 855

Unnumbered paragraph

~ therefore, was misread and misconstrued. ...

p. 855

Unnumbered paragraph

82. In Premji Bhai Parmar (supra), surcharge was a component of the disposal price. The disposal price was known to the registrants at the time of conclusion of contract. As the contract was found to be binding c on the parties, levy of surcharge, thus, was held to be vitiated in law.

p. 855

Unnumbered paragraph

83. In this case, the case of the appellant is not that they are not bound to pay the binding contractual stipulation as contained in Clause 4 of the letter of allotment. They are and they must. But what cannot be thrust on them is the price determined on the basis of factors which were not contemplated in the original contract.

p. 855

Unnumbered paragraph

84. In Premji Bhai Parmar (supra), this Court did not record a finding that even if a surcharge was not a part of Brochure, still the same could be imposed without any sanction in law so as to bind the allocates to pay the same although neither they were made aware thereof nor did they give their consent for payment of surcharge as a part of the contract. The Full Bench of the High Court wrongly relied upon R.K. Sachar

p. 855

Unnumbered paragraph

(supra). In the light of the decision of this Court in Premji Bhai Parmar ,....

p. 855

Unnumbered paragraph

(supra), the nature oflevy should have been held to be completely distinct " F and, thus, Premji Bhai Parmar (supra) had no application to the fact of the present case.

p. 855

Unnumbered paragraph

85. The Full Bench also misdirected itself insofar as it failed to take into consideration that levy of20% surcharge was in effect and substance

p. 855

Unnumbered paragraph

a compulsory exaction to augment the revenue requirements of the DDA G ~ and, thus, could not have been a part of the contract. Any compulsory

p. 855

Unnumbered paragraph

exaction should be viewed in the light of Article 265 of the Constitution -- oflndia, unless it comes within the sphere of contract.

p. 855

Unnumbered paragraph

86. It may be reiterated that it is only those components which fall A within the Brochure of the DDA or within the purview of the statutory requirements can be included in the exercise of price fixation. To the said extent are the decision of the Delhi High Court in P.N Verma (supra), Narsingh Jain v. Union of India [(80) (1999) DLT 742) and DDA SFS Flat Owners Society v. UOI, AIR (2001) Del 39).

pp. 855–856

Unnumbered paragraph

87. Against the said judgment of the Division Bench of the High Court in P.N Verma (supra), an appeal was preferred by the DDA before this Court. This Court in the said appeal titled as DDA v. SFS Assn. and • Ors. [Civil Appeal No. 4402of1985) rejected the contention of the DDA

p. 856

Unnumbered paragraph

that under the terms of the Brochure related to the said scheme it was empowered to recover from the registrants an additional amount over and above the disposal price by way of equalization charges in the following terms:

p. 856

Unnumbered paragraph

"The lengthy and elaborate judgment of the High Court under appeal makes instructive reading in prohibiting the DDA from adding to the prices of the named flats on escalation termed as 'equalisation and ad hoc charges'. From the terms of the model contract entered into by the DDA with the people who opted for the self-financing scheme, charging of the said equalization and ad hoc charges is evidently totally missing. The DDA in support thereof has banked upon the justness of its cause and demand, and has no where been able to project that to begin with, it was part and parcel of the cost factor. The High Court has seen through its design and has termed the venture as a camouflage. We see no reason to take a different view than the one taken by the High

p. 856, margin C

Unnumbered paragraph

.... F Court."

p. 856, margin C

Unnumbered paragraph

The said decision of this Court is binding upon the DDA. Conclusion :

p. 856, margin C

Unnumbered paragraph

88. For the reasons aforementioned, the impugned judgment cannot be sustained which is set aside accordingly. The appeals are allowed with costs. Counsel's fee assessed at Rs. 25,000/- in each case. Appeals filed by the DDA are dismissed.

p. 856, margin C

Unnumbered paragraph

K.K.T. Appeals filed by registrants allowed. H Appeals filed by DDA dismissed.

p. 856, margin C