Certo Is this judgment real?
Beta, Supreme Court only. We check Supreme Court of India judgments only for now: a High Court citation reads "Not in our corpus", which never means it does not exist.

Supreme Court of India

S.M. NILAJKAR AND ORS. versus TELECOM DISTRICT MANAGER, KARNATAKA

Decided
31 March 2003
Judges listed
R.C. LAHOTI (as the open data lists them; this may not name the whole bench)
Disposal
Appeal(s) allowed

Citations

Official
[2003] 3 S.C.R. 156 · 2003 INSC 195
Also cited as
  • (2003) 4 SCC 27 (83 citing judgments)
  • AIR 2003 SC 3553 (11 citing judgments)
  • (2003) SCC(L&S) 380 (11 citing judgments)
  • JT 2003 (3) SC 436 (5 citing judgments)

Learned from how other judgments cite this one, in their text or in the official Supreme Court Reports' lists of cases they refer to: each is cited this way by at least two judgments, and at least twice as often as any other citation to this judgment in that report. We hold no commercial reporter's text, only these citation strings.

Not shown
3 other citation strings that other judgments attach to this one, on evidence too thin or too divided to publish.

Cited by

Cited in 16 other Supreme Court judgments we hold. The 5 most recent:

Counted only in the Supreme Court judgments we hold whose text we could read, not in High Court judgments. We match each citation to a judgment automatically, so a citation we cannot match is not counted. "Cited" says only that a judgment refers to this one, not whether it followed, distinguished or overruled it.

The Court's text

Paragraphs from our copy of the Supreme Court Reports print, with the Court's own paragraph numbers, the printed page and, where printed, the margin letter. The Court did not number this judgment's paragraphs, so they are listed by page. Link to paragraph N with #para-N.

Unnumbered paragraph

R.C. LAHOTI, J. A number of workers were engaged as casual lab.ourers for the purpose of expansion of telecom facilities in the district of Belgaum, Karnataka, during the years 1985-86 and 1986-87, The services of these workers were utilized for digging, laying cables, erecting poles, drawing lines and other connected works. It appears that the services of these workmen were terminated sometime during the year 1987 and they were not engaged on work thereafter. In Daily Rated Casual labour employed under P& T Deptt. tlirough Bhartiya Dak Tar Ma::door Manch v, Union of India and Ors., [I 988] I SCC 122, the Supreme Court by its judgment dated 27.10.1987 directed the Depa11ment to fonnulate a scheme under which all casual labourers who had rendered more than one year's continuous service could be absorbed, Pursuant to the said directions, the Department of Telecommunications formulated a scheme called "Casual labourers (Grant of Temporal)' Status and Regularisation) Scheme, 1989" which came into force w.e.f. 0L10.1989. A list of casual labourers was drawn up for inclusion under the said scheme, On 16.0L1990, a number of workers whose names were not included for regularization under the said scheme, raised disputes before the Assistant Labour Commissioner, Mangalore. Conciliation proceedings were initiated but they failed. Several disputes were referred for adjudication by the Labour Court in the years 1994 to 1997. The disputes which were referred were almost identically framed. In substance, the dispute was 'whether the termination of the services of (name of worker) w.e.f. (a date in 1986 or 1987), Casual Mazdoor by the Management of Telecom District Manager, Belgaum is justified or not If not, to what relief the workman is entitled?'

pp. 160–161, margin H

Unnumbered paragraph

A consolidated enquiry was held into all the disputes and they were disposed of by a common award dated 21.06.1999 by the Central Government Industrial Tribunal-cum-Labour Court, Bangalore. The Tribunal directed the employer to reinstate all the workmen into service, with the benefit of continuity of service and with 50% of back wages. The employer filed ten writ petitions in the High Court of Karnataka which were disposed of on 16.09.1999 by a common judgment delivered by a learned Single Judge. The learned Single Judge held that the workers were not project employees as contended by the employer. The appointment was not for any particular project and hence would not be governed by sub-clause (bb) of clause (oo) of Section 2 of the Industrial Disputes Act. 1947 (hereinafter 'the Act' for short). Of the workmen each had rendered a continuous service within the meaning of Section 25B of the Act for a period over 240 days and, therefore, their termination amounted to retrenchment which was invalid for noncompliance with Section 25F of the Act. The workmen were, therefore, entitled to reinstatement. However, there was a delay of nearly 7 to 9 years in raising the disputes. The workmen had not placed any material on record to hold that there was no delay and the disputes were promptly raised. It was because of this delay that th1e employer was not in a position to produce the record relating to the days for which the workmen had worked inasmuch as according to the standing instructions of the Department, the registers of muster rolls were preserved for a period of 5 years only, whereafter they were eliminated. The Tribunal did not err in believing the oral evidence adduced by the workmen as to the period of their employment (i.e. for over 240 days). On account of delay in raising the dispute, the High Court held that the workmen were not entitled to any back wages. The learned Single Judge directed the award to be modified to that extent and upheld the Tribunal's award to the extent tv which it directed reinstate1ni:nt with the benefit of continuity of service and consequential benefits but without back wages.

pp. 161–162, margin E

Unnumbered paragraph

The employer filed intra-court writ appeals under Section 4 of the Karnataka High Court Act, which were heard and disposed of by a Division Bench of the High Court vide the impugned order dated 9.02.2000. Before the Division Bench, it was an admitted case of the parties that the workmen were employed by the Telecom Department as casual labourers in connection with a project for ·extension of telecom facilities in the district of Belgaum. Their services were utilized for digging, laying of coaxial cables and other sundry work. The project was completed sometime in the year 1986-87. The disputes were raised after a lapse of 7 to 9 years.

p. 162, margin C

Unnumbered paragraph

Before the Division Bench, the employer placed reliance on Circular No. 270/6/84-STM dated 30.03.1985 issued by the Director General (Posts & Telegraphs), New Delhi to all heads of telecom circles etc. The Circular reads as under :- Copy of Le1ter No.270/6/84-STN, dated 30.3.1985 from the DG P&T, New Delhi to All Heads of Te!.ecom Circles., Etc.

p. 162, margin E

Unnumbered paragraph

Sub. Casual labour-engagement Sir.

p. 162, margin F

Unnumbered paragraph

15.6.80 A number of instructions have been issued from time to time stressing the need to limit the number of casual labour employed by the Telecom Units to a minimum. It is, however, regretted to note that inspite of these instructions. the number of such casual labours in Telecom. Circles/Districts is increasing.

pp. 162–163, margin G

Unnumbered paragraph

2. The position has been reviewed and it has been decided that fresh recruitment and employment of casual labour for any type of work should be stopped forthwith in Telecom Circles/Districts. The casual labour already in employment should be utilized only (I) for work of casual nature, (2) all installation works of temporary nature, (3) cable laying work and (4) lines construction/dismantling work. Regular posts of Mazdoors/Group 'D' posts are sanctioned for maintenance/Admn. Work as per standards already laid down by this office from time to time. As such, no casual mazdoors are required for utilized for maintenance/office work, they should be reallotted/ transferred and used in the works enumerated above. Every effort should be made to reduce the number of casual mazdoors employed and in no case fresh recruitment/employment made.

p. 163, margin A

Unnumbered paragraph

3. These orders would, however, not apply to the coaxial cable laying work in the projects organization and in line dismantling/ constructions work in the Electrification Projects Circle. The casual labour for such works in these units could be engaged only for specific jobs and retrenched as soon as the work is over.

p. 163, margin C

Unnumbered paragraph

4. The Heads of Telecom Circles/districts may take immediate action to bring these instructions to the notice of all subordinate units for strict adherence. The receipt of this letter may please be acknowledged. xxx xxx xxx xxx They should ensure that no fresh recruitment and employment of casual mazdoors for any type of work is made in future. All subordinate units may be instructed suitably. They should acknowledge the receipt of this communication by next post.

p. 163, margin D

Unnumbered paragraph

Sd/- For General Manager, Telecom.

p. 163, margin G

Unnumbered paragraph

Karnataka Circle, Bangalore-9"

p. 163, margin G

Unnumbered paragraph

Another Circular No. 269-29/87-STM dated 10th November 1988 issued

p. 163, margin G

Unnumbered paragraph

the Government of India, Ministry of Communications, Department of Telecommunications, New Delhi, was relied on, dealing with the subject of regularization of casual labourers. Guidelines for eligibility for regularization of casual labourers as against 14. 117 posts of regular mazdoors (group · D') for various circles were laid down. Out of several eligibility conditions. one was that the casual labourer/ part-time casual labourer should have served the Department for a minimum period of 7 years as on 31.03.1986. Admittedly, the respondent workmen did not satisfy this eligibility condition.

pp. 163–164, margin G

Unnumbered paragraph

The Division Bench held that the workmen (respondents before it) were employed under a project of the Telernm Department and were. therefore. covered by sub-clause (bb) of clause ( oo) of Section 2 of the Act. It was a clear case of termination of services of the workmen as a result of nonrenewal of contract of employment on the expiry of the contract. The question of compliance of Section 25F of the Act did not arise. The respondentworkmen could not be said to have been retrenched. The engagement of the workmen was on daily wages and only for the purpose of completion of the project undertaken by the Telecom Department for laying coaxial cables in the Belgaum District. That the project had been completed in 1986-87 itself, is not in dispute. Because of completion of the project their services stood terminated ipso facto. The Department's Circular dated 30.03.1985 was relied upon. The Division Bench placed reliance on decisions of this Court in Gha:iabad Development Authority am/ Ors. v. Vikram Choudhary & Ors .. [ 1995] 5 sec 210 and Executive Engineer. State ojKarnataka v. K. Somasetty and Ors., [1997] 5 sec 434 for forming the opinion that the workmen could not be said to have been illegally retrenched. The Division Bench also formed the opinion that unexplained and undue delay of 7 to 9 years in raising the disputes before the Tribunal vitiated the reference because of !aches. For taking this view, reliance was placed on Shalimar Works Ltd. v. Their

p. 164, margin B

Unnumbered paragraph

Workmen. [1960] I SCR 150. Ratan Chandra Sammon/av. Union of India, [ 1993] Supp. 4 SCC 67 and Nedungadi Bunk Ltd v. K. P. Madhavankutty & Ors .. [2000] 2 sec 455. The Division Be1ch allowed the appeals preferred by the employer and directed the award of the Tribunal as also the judgment of the learned Single Judge to be set aside.

p. 164, margin E

Unnumbered paragraph

Feeling aggrieved by the judgment of the Division Bench, these ten appeals have been filed by the workers by special leave.

p. 164, margin G

Unnumbered paragraph

The learned counsel for the workmen-appellants have submitted that the workmen were employed for general maintenance work of the Telecom Department and not in any project work. There are two types of organizations in Telecom Department, namely, (i) Telecom Circles and, (ii) Telecom Project Circles. The workmen were employed in Karnataka Te_lecom Circie, Belgaum Division. The Circular dated 30.03.1985 has no application to these workmen. The disputes were promptly raised and pursued. The reference sought for by the workmen cannot be said to be delayed or suffering from lapse, particularly when the law does not prescribe any period of limitation for raising a limitation under Section I 0 of the Act. It was, therefore, submitted that the award as given by the Tribunal was not liable to be interfered with. On behalf of the employer-respondent, the same pleas have been reiterated as were taken before the Tribunal and the High Court. It is submitted that the workmen are project employees whose services are liable to be dispensed with ipso facto on termination of the project and that the Division Bench of the High Court has rightly held the disputes raised by the workmen to be vitiated by delay and I aches.

pp. 164–165, margin G

Unnumbered paragraph

Let it be stated that on the material available we are not inclined to upset the finding of fact arrived at in the impugned judgment that the appellant workmen are project employees and not employed in any department. The principal issue argued by the learned counsel for the parties centers around the status of project or scheme employees - whether the workmen recruited for discharging temporary job under a project can insist on compliance of Section 25F of the Act if their services are dispensed with on the project coming to an end9

p. 165, margin C

Unnumbered paragraph

Section 2(oo) and 25F of the Act, relevant for our purpose, provide as under:

p. 165, margin E

Unnumbered paragraph

2. Definitions : In this Act, unless there is anything repugnant in the subject or context, xxx xxx xxx xxx [(oo) "retrenchment" means the termination by the employer of the service of a workman for any reason whatsoever, otherwise than as a punishment inflicted by way of disciplinary action, but does not include- (a) voluntary retirement of the workman; or (b) retirement of the workman on reaching the age of superannuation if the contract of employment between the employer and the workman concerned contains a stipulation in that behalf; or [(bb) termination of the service of a workman as a result of the nonrenewa:I of the contract of employment between the employer and the workman concerned on its expiry or of such contract being terminated under a ~;tipulation in that behalf contained

pp. 165–166, margin E

Unnumbered paragraph

therein; or] (c) termination of the service of a workman on the ground of

p. 166, margin A

Unnumbered paragraph

continued ill-health r "25F. Conditions precedent to retrenchment of workmen.-No workman employed :n any industry who has been in continuous service for not less than one year under an employer shall be retrenched by that employer until-- (a) the workman has been given one month's notice in writing indicating the reasons for retrenchment and the period of notice has expired, or the workman has been paid in lieu of such notice, wages for the period of the notice', (b) the workman has been paid. at the time of retrenchment, compensation which shall be equivalent to fifteen days' average pay [for every completed year of continuous service] or any part thereof in excess of six months; and ( c) notice in the prescribed manner is served the appropriate Government [or such authority as may be specified by the appropriate Government by notification in the Official Gazette]."

p. 166, margin B

Unnumbered paragraph

It is common knowledge that the Government as a welfare State floats severa 1 schemes and projects generating employment opportunities, ti ough they are short-lived. The objective is to meet the need of the moment. The benefit of such schemes and projects is that for the duration they exist, they provide employment and livelihood to such persons as would not have been able to sec1:re the same but for such schemes or projects. If the workmen employed for fulfilling the need of such passing-phase-projects or schemes were to become a liability on the employer-State by too liberally interpreting the labour laws in favour of the workmen, then the same may well act as a disincentive to the State for floating such schemes and the State may opt to keep away from initiating such schemes and projects even in times of dire need, because it may feel that by opening the gates of welfare it would be letting-in onerous obligations entailed upon it by extended application of the labour laws. Sub-clause (bb) in the definition of retrenchment was introduced to take care of such like-situations by Industrial Disputes (Amendment) Act, 1984 with effect from I 8.8.1984.

pp. 166–167, margin E

Unnumbered paragraph

'Retrenchment' in its ordinary connotation is discharge of labour as surplus though the business or work itself is continued. It is well-settled by a catena of decisions that labour laws being beneficial pieces of legislation are to be interpreted in favour of the beneficiaries in case of doubt or where it is possible to take two views of a provision. It is also well-settled that the Parliament has employed the expression "the termination by the employer of the service of a workman/or any reason whatsoever" while defining the term "retrenchment", which is suggestive of the legislative intent to assign the term 'retrenchment' a meaning wider than what it is understood to have in common parlance. There are four exceptions carved out of the artificially extended meaning of the term 'retrenchment', and therefore, termination of service of a workman so long as it is attributable to the act of the employer would fall within the meaning of 'retrenchment' de hors the reason for termination. To be excepted from within the meaning of 'retrenchment' the termination of service must fall within one of the four excepted categories. A termination of service which does not fall within the categories (a), (b), (bb) and (c) would fall within the meaning of 'retrenchment'.

p. 167, margin A

Unnumbered paragraph

The termination of service of a workman engaged in a scheme or project may not amount to retrenchment within the meaning of sub-clause (bb) subject to the following conditions being satisfied :- (i) that the workman was employed in a project or sch~me of

p. 167, margin E

Unnumbered paragraph

temporary duration; (ii) the empioyment was on a contract, and not as a daily-wager simplicitor, which provided inter alia that the employment shall

p. 167, margin E

Unnumbered paragraph

come to an end on the expiry of the scheme or project; and (iii) the employment came to an end simultaneously with the termination of the scheme or project and consistently with the

p. 167, margin F

Unnumbered paragraph

terms of the contract; (iv) the workman ought to have been apprised or made aware of the abovesaid terms by the employer at the commencement of employment.

p. 167, margin G

Unnumbered paragraph

The engagement of a workman as a daily-wager does not by itself amount to putting the workman on notice that he was being engaged in a scheme or project which was to last only for a particular length of time or upto the occurrence of some event. and therefore, the workman ought to know that his employment was short-lived. The contract of emplo;nnent consciously entered into by the workman with the employer would result in a notice to the workman on the date of the commencement of th~ employment itself that his employment was short-lived and as per the terms of the contract the same was liable to termination on the expiry of the contract and the scheme or project coming to an end. The workman may not therefore complain that by the act of employer his employment was coming to an abrupt termination. To exclude the termination of a scheme or project employee from the definition ofretrenchment it is for the employer to prove the abovesaid ingredients so as to attract the applicability of sub-clause (bb) abovesaid. In the case at hand, the respondent-employer has failed in alieging and proving the ingredients of sub-clau~.e (bb), as stated hereinabove. All that has bc·cn proved is that the appellants were engaged as casual workers or daily-wagers in a project. For want of i:roof attracting applicability of sub-clause (bb), it has to be held that the termination of the services of the appellants amounted to retrenchment.

p. 168, margin A

Unnumbered paragraph

The appropriate provision which should govern the cases of the appellants is Sectwn 25FFF, the relevant part whereof is extracted and reproduced hereunder:- "25 FFF. Compensation to workmen in case of closing down of undertakings,-( I) Where an undertaking is closed down for any reason whatsoever, every workman who has been in continuous service for not less than one year in that undertaking immediately before such closure shall, subject to the provisions of sub-section (2), be entitled to notice and compensation in accordance with the provisions of section 25F, as if the workman had been retrenched: Provided that '.vherc the undertaking is closed down on account of unavoidable circumstances beyond the COl'trol of the employer. 1he compensation to be paid to the workman under clause (b) of sectic,n 25F shall not exceed hi~. average pay for three months. {Explanation: An undertaking v.hich is closed down by reason merely of (i) financial difficulties (including financial losses); or (ii) accumulation of undisposed of stocks; or (iii) the expiry of the period of the lease or licence granted to it; or (iv) in a case where the undertaking is engaged in mining operations, exhaustion of the minerais in the area in which such operations

pp. 168–169, margin D

Unnumbered paragraph

are carried on, shall not be deemed to be closed down on account of unavoidable circumstances beyond the control of the employer within the meaning of the proviso to this sub-section.] IA. [Not reproduced] IB. [Not reproduced] (2) Where any undertaking set-up for the construction of buildings, bridges, roads, canals, dams or other construction work is closed down on account of the completion of the work within two years from the date on which the undertaking had been set up, no workman employed therein shall be entitled to any compensation under clause (b) of section 25F, but if the construction work is not so completed within two years, he shall be entitled to notice and compensation under that section for every [completed year of continuous service] or any part thereof in excess of six months."

p. 169, margin B

Unnumbered paragraph

It is pertinent to note that in Hariprasad Shivshanker Shukla and Anr. v. A.D. Divikar and Ors., [ 1957] SCR 121 the Supreme Court held that 'retrenchment' as defined in Section 2(oo) and as used in Section 25F has no wider meaning than the ordinary accepted connotation of the word, that is, discharge of surplus labour or staff by the employer for any reason whatsoever otherwise than by way of punishment inflicted in disciplinary action. Retrenchment was held to have no application. where the services of all workmen were terminated by the employer on a real and bona fide closure of business or on the business or undertaking being taken over by another employer. The abovesaid view of the law taken by the Supreme Court r"sulted in promulgation of the Industrial Disputes (Amendment) Ordinance. 1957 with effect from 27.4.1957, later on replaced by an Act of ParliJm"m (Aci 18 of 1957) with effect from 6.6.1957 whereby Section 25FF and Sc.:liG11 25FFF were introduced in the body of the Industrial Disputes Section 25FF deals with the case of transfer of undertakings are not concerned. Section 25FFF deals with closing down The term 'undertaking' is not defined in the Act. The relevant provisions the term 'industry'. Undertaking is a concept narrower than undertaking may be a part of the whole, that is, the industry. restricted meaning. (see Bangalore Water Supply & Sewerage Board etc. A. Rajappa and Ors. etc., [I 978] 2 SCC 213 and the Management Steel Ltd v. The Workmen and Ors., (1973] 3 SCC 564. With it is clear that closure of a project or scheme by the State Government be covered by closing down of undertaking within the meaning 25FFF. The workman would therefore be entitled to notice in accordance with the provisions of Section 25F though the to close the undertaking for any reason whatsoever cannot Compliance of Section 25F shall be subject to such relaxations by Section 25FFF. The undertaking having been closed unavoidable circumstances beyond the control of the employer, own force as it was designed and destined to have a limited compensation payable to the workman under clause (b) of not exceed his average pay for three months. This is so because of failure the part of respondent employer to allege and prove that employment fell within sub-Clause(bb) of Clause (oo) of Act.

pp. 169–170, margin E

Unnumbered paragraph

It was submitted on behalf of the respondent that on in raising the dispute by the appellants the' High Court was justified relief to the appellants. We cannot agree. It is true, as held Works Limited v. Their Workmen (supra) that merely because Disputes Act does not provide for a limitation for raising not medn that the dispute can be raised ar. any time and without regard delay and reasons therefor. There is no limitation prescribed disputes to an industrial tribunal; even so it is only reasonable should be referred as soon as possible after they have conciliation proceedings have failed particularly so when discharge of workmen wholesale. A delay of 4 years in raising after even re-employment of the most of the old workmen fatal in Mis Shalimar Works Limited v. Their Workmen (supra). Ba11k ltd v. K.P. Madhavankutty and Ors. (supra), a delay held to be fatal and disentitled the workmen to any relief.

p. 170, margin E

Unnumbered paragraph

Sammanta and Ors. v. Union of India and Ors., (supra), it was held that a casual labourer retrenched by the employer deprives himself of remedy available in law by delay itself; lapse·of time results in losing the remedy and the right as well. The delay would certainly be fatal if it· has resulted in material ev'idence relevant to adjudication being lost and rendered not available. However, we do not think that the delay in the case at hand has been so culpable as to disentitle the appellants for any relief. Although the High Court has opined that there was a delay of 7 to 9 years in raising the dispute before the Tribunal but we find the High Court factually' not correct. i'he employment of the appellants was terminated sometime in 1985-86 or 1986' 87. Pursuant to the judgment in Daily Rated Casual Employees Under P & T Department v. Union of India, (supra) the department was formulating a· scheme to accommodate casual labourers and the appellants were justified in awaiting the outcome thereof. On 16.1.1990 they were refused to be accommodated in the scheme. On 28.12.1990 they initiated the proceedings under the Industrial Disputes Act followed by conciliation proceedings and then the dispute was referred to the Industrial Tribunal-cum-Labour Court. We do not think that the appellants deserve to be non-suited on the ground of delay.

p. 171, margin A

Unnumbered paragraph

The fact remains that there was delay, though not a fatal one, in initiating proceedings calculating the time between the date of termination and initiation of proceedings before the Industrial Tribunal-cum-Labour Court. The employee cannot be blamed for the delay. The learned Single Judge has denied the relief of back-wages while directing ti'e appellants to be reinstated. That appears to be a just and reasonable order. Moreover, the judgment of the learned Single Judge was r.ot put in issue by the appellants by filing an appeal.

p. 171, margin D

Unnumbered paragraph

For all !he foregoing reasons we are of the opinion that the decision of the Division Bench deserves to be set aside and that of the learned Single Judge restored, except for the finding that the appellants were not project employees.

p. 171, margin F

Unnumbered paragraph

During the course of hearin!l it was stated at the Bar that there are a number of matters pending in different fora, Industrial-cum-Labour Court or High Court, raising similar issues a1~aiting decision in this case. We clarify that all such pending cases shall be heard and decided in accordance with the law as stated hereinabove. The project in which the workmen were engaged has come to an end. The respondent Government may consider the appellants A being accommodaied in some other project or scheme or regular employment, if available, by issuing suitable instructions or guidelines. If it be not possible, the respondent shall be at liberty to terminate the employment of the appellants after reinstating them as directed by the High Court and then complying with Section 25F of the Industrial .Disputes Act.

pp. 171–172, margin G

Unnumbered paragraph

The appeals are allowed. The impugned decision of the Division Bench is set aside and that of the learned single Judge is restored as above. The appellants shall be entitled to their costs throughout. K.K.T. Appeals allowed.

p. 172