Certo Is this judgment real?
Beta, Supreme Court only. We check Supreme Court of India judgments only for now: a High Court citation reads "Not in our corpus", which never means it does not exist.

Supreme Court of India

M/S BSES LTD. (NOW RELIANCE ENERGY LTD.) versus M/S FENNER INDIA LTD: AND ANR.

Decided
3 February 2006
Judges listed
H.K. SEMA (as the open data lists them; this may not name the whole bench)
Disposal
Appeal(s) allowed

Citations

Official
[2006] 2 S.C.R. 47 · 2006 INSC 69
Also cited as
  • (2006) 2 SCC 728 (16 citing judgments)
  • AIR 2006 SC 1148 (2 citing judgments)

Learned from how other judgments cite this one, in their text or in the official Supreme Court Reports' lists of cases they refer to: each is cited this way by at least two judgments, and at least twice as often as any other citation to this judgment in that report. We hold no commercial reporter's text, only these citation strings.

Not shown
2 other citation strings that other judgments attach to this one, on evidence too thin or too divided to publish.

Cited by

Cited in 1 other Supreme Court judgment we hold.

Counted only in the Supreme Court judgments we hold whose text we could read, not in High Court judgments. We match each citation to a judgment automatically, so a citation we cannot match is not counted. "Cited" says only that a judgment refers to this one, not whether it followed, distinguished or overruled it.

The Court's text

Paragraphs from our copy of the Supreme Court Reports print, with the Court's own paragraph numbers, the printed page and, where printed, the margin letter. The Court did not number this judgment's paragraphs, so they are listed by page. Link to paragraph N with #para-N.

Unnumbered paragraph

SRIKRISHNA, J. Leave granted.

p. 50, margin B

Unnumbered paragraph

This is one more instance of an injunction being sought against a beneficiary seeking to enforce his/her rights under a bank guarantee, <>lbeit with a novel averment that "lack of good faith" or "enforcing with an oblique purpose" constituted further exceptions to the general rule against intervention. The Facts

p. 50, margin B

Unnumbered paragraph

Mis Godavari Sugars Ltd. awarded a contract for a captive power plant to Mis BSES Ltd. (now Reliance Energy Ltd.) (hereinafter "the Appellant"). The Appellant, in turn, awarded a part of that work to Mis Fenner India Ltd. (hereinafter "the First Respondent"). In connection with this, the Appellant issued to the First Respondent, four work orders/ purchase orders, as follows:

p. 50, margin C

Unnumbered paragraph

"(i) Work Order No. 2245 dated 15.3.2000/ 4.5.2000 for a sum of

p. 50, margin D

Unnumbered paragraph

Rs. 70,00,000/~ (ii) Work Order No. 2246 dated 15.3.2000/ 4.5.2000 for a sum of

p. 50, margin D

Unnumbered paragraph

Rs.5,57,00,000/- (iii) Work Order No. 2247 dated 15.3.2000/ 4.5.2000 for a sum of

p. 50, margin E

Unnumbered paragraph

Rs.90,00,000/- (iv) Work Order No. 2248 dated 15.3.2000/ 4.5.2000 for a sum of

p. 50, margin E

Unnumbered paragraph

Rs.50,00,000/-..... "

p. 50, margin F

Unnumbered paragraph

As required by the terms and conditions of the s.iid work/ purchase orders, the First Respondent submitted four bank guarantees from the State Bank of India (hereinafter "the Second Respondent-Bank"), dated 23.3.2000 bearing, Nos. 288/99, 289/99, 290/99 and 291/99 in sums of Rs. 7,00,000/-, Rs. 9,00,000/-, Rs. 55,70,000/- and Rs. 38,35,000 respectively. They were unconditional irrevocable bank guarante·~s, under which the Second Respondent-Bank agreed to pay to the Appellant the amount claimed or demanded by the Appellant. The amounts guarantei!d thereunder were payable with or without any reason in writing from the Appellant, without protest or demur or proof of satisfaction, and without reference to the First Respondent, upon being called by the Appellant, irrespective of any dispute between the Appellant and the First Respondent with regard to or touching any of the contractual tenns between them. They were, of course, subject to the aggregate limits stipulated,_ iQ each of the bank guarantees. ''"'"'

pp. 50–51, margin F

Unnumbered paragraph

: . ; ' ' . . ' l · ~;

p. 51, margin A

Unnumbered paragraph

On I0.5.2000, the Appellant and the First Respondent entered into "wrap-around agreement", under which it was agreed that the First Respondent would perfonn its contractual obligations on a turnkey basis viz. as a composite one. This principle was also made applicable to the bank guarantees. Thus, Clause (4) of this agreement in tenns says:

p. 51, margin A

Unnumbered paragraph

"In case of any material breach of any or all the Contracts, BSES sh.all have the right to embark upon the retentions and encashment of ... Bank Guarantees of all the contracts."

p. 51, margin B

Unnumbered paragraph

On 4.12.2003; the Appellant invoked the four bank guarantees. On 7.122003, the First Respond~nt. invoked the arbitration clause, as provided in the work/ purchase orders. On 8.12,2003, the First Respondent moved petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereinafter "the Arbitration Act") before the District Court, M<tdurai, seeking a declaration that the Appellant was not entitled to invoke the four bank guarantees. The First Respondent also sought an interim injunction against the Appellant restraining them from encashing or receiving any amount under the bank guarantees, pending disposal of the arbitration proceedings.

p. 51, margin C

Unnumbered paragraph

On 22.3.2004, the learned Principal District Judge, Madurai, dismissed the First Respondent's petition by holding that this was not a case where "irretrievable injustice" would be done by enforcement of the bank guarantees, nor was it a case where a strongprimafacie case of fraud had been made out. Despite this finding, the learned District Judge took the view that, although the Appellant was not entitled to an order of injunction, the Appellant's rights would have to be safeguarded till the matter was disposed of in the arbitration proceedings. Accordingly, the learned District Judge directed the Appellant to maintain status quo for a period of one month (from the date the order), within which the arbitral proceedings were to be disposed of. The parties were directed to seek their remedies before the arbitrator.

p. 51, margin E

Unnumbered paragraph

Sometime in April 2004, an application was made under Section 17 the Arbitration Act before the Arbitral Tribunal. The First Respondent preferred an appeal before the High Court of Madr11s challenging the order and judgment dated 22.3.2004 of the learned District Judge. On 24.5.2004, even while-the arbitral proceedings were pendi11g, the High Court made an interim order. Further, by the impugned judgment dated 30. 7 .2004, the High Court allowed the appeal preferred by the First Respondent and granted the injunction as prayed for, and set aside the order of the learned District Judge. The Rule and its Exceptions

pp. 51–52, margin G

Unnumbered paragraph

Mr. Rohtagi, learned Senior Counsel for the Appellant, urged that the settled law in this country is that a bank guarantee is an independent contract between the bank and the beneficiary thereof. Accordingly, irrespective of any dispute between the beneficiary and the party at whose instance the bank has given the guarantee, the bank is obliged to honour its guarantee, as long as the guarantee is unconditional and irrevocable. Our attention was drawn to the judgment of this Court in UP. Cooperative Federation ltd. v. Singh Consultants and Engineers (P) Ltd.' (hereinafter "U.P. Cooperative Federation"). It was pointed out in that case that a bank guarantee must be honoured in accordance with its terms as the bank, which gives the guarantee, is not concerned with the relations between the supplier and the customer. Neither is the bank concerned with the question whether any of them have failed in their contractual obligations or not. In other werds, the bank must pay according to the tenor of its guarantee, on demand, without proof or condition.

p. 52, margin B

Unnumbered paragraph

There are, however, two exceptions to this rule. The first is when there is a clear fraud of which the bank has notice and a fraud of the beneficiary from which it seeks to benefit. The fraud must be of an egregious nature as to vitiate the entire underlying transaction. The second exception to the general rule of non-intervention is when there are "special equities" in favour of injunction, such as when "irretrievable injury" or "irretrievable injustice" would occur if such an injunction were not granted. The general rule and its exceptions has been reiterated in so many judgments of this Court that in UP. State Sugar Corporation v. Sumac International ltd, (hereinafter "UP. State Sugar Corporation") this Court, correctly declared that the law was '(198811 sec 114. 'See, eg., State Sugar Corporation Sumac International ltd .. [1997) I SCC 568 at pp. 574-577 (paragaraphs 12-16), State of Maharashtra v. National Construction Co., Bombay, [1996) I SCC 735 at 741(paragraph13). See. also United Commercial Bank Bank of India, (1981) 2 SCC 766 and Centax (India) ltd. v. Vinmar lmpexlnc., [1986) 4 sec 136. '1199711 sec 568.

p. 52, margin E

Unnumbered paragraph

"settled"

p. 53, margin A

Unnumbered paragraph

Mr. Sorabjee, however, tried to expand upon the settled exceptions to the rule by first, relying on an order of this Court in State of Haryana v. Continental Construction ltd (hereinafter "Continental·Construction ltd") . We are afraid that the short order in Continental Construction Ltd (supra) appears to have been made on the narrow facts of that case and does not constitute a precedent binding us. Moreover, as mentioned earlier, a line of judgments of this Court have long settled the law relating to the invocation of bank guarantees.

p. 53, margin A

Unnumbered paragraph

Second, Mr. Sorabjee placed reliance on a number of foreign judgments, especially that of the Queen's Bench Division in IT/ Team Telecom Ltd v. Hutchison 3G UK Ltd, wherein, the rule and its exceptions in England have been elegantly summarized. Mr. Sorabjee placed special emphasis on the following propositions:

p. 53, margin C

Unnumbered paragraph

" ... (3) The basis for a contention of a breach of faith must be established by clear evidence even for the purposes of interim relief. A breach of faith can arise in such situations as: a failure by the beneficiary to provide an essential element of the underlying contract on which the bond depends; a misuse by the beneficiary of the guarantee by failing to act in accordance with the purpose for which it was given; a total failure of consideration in the underlying contract; a threatened call by the beneficiary for an unconscionable ulterior motive; or a lack of an honest or bona fide belief by the beneficiary that the circumstances, such as poor performance, against which a performance bond had been provided, actually exist. (4) In addition, where it appears that the call would be a nullity, a court will intervene to restrain that invalid call. Examples are where a condition precedent to a call has not yet been fulfilled; where the bond is a 'see to it' bond necessitating prior proof of loss by the sec sos.

p. 53, margin C

Unnumbered paragraph

and and beneficiary or poor performance by the third party which has not yet been established; or where the demand or the supporting documents show that the demand does not conform to the requirements imposed by the bond for a valid demand. (5) Otherwise, a threatened call will not be restrained. In particular an allegedly incorrect calling of a performance bond will not be restrained merely because the factual basis of the call arising out of the underlying contract is disputed. Thus disputes as to whether a breach of contract, a determination of a contract for cause, a repudiation of a contract or the incurring of loss have occurred, where these are events covered by the performance guarantee, will not be allowed to found an application to restrain a call unless these disputes reveal a breach of faith by the beneficiary. Any consequent payment under the bond ~o the beneficiary which over-compensates the beneficiary may be recouped in the 'accounting' exercise that the third party may claim in subsequent litigation against the beneficiary under the underlying contract. .... "

pp. 53–54, margin G

Unnumbered paragraph

Mr. Sorabjee, finally contended that in Singapore, where commercial cases are expeditiously disposed of, the Court of Appeal in Samwoh Asphalt Premix Pte. Ltd v. Sum Cheong Piling Pte. Ltd' has held that calling a performance guarantee for an oblique purpose was not permissible. Specifically, using it as a "bargaining chip", as a "deterrent" or in an "abusive" manner, would invite an injunction from the court. He submitted that the Singapore court has gone so far as to say that the unconscionable calling of a bank guarantee was an exception i.ndependent of fraud.

p. 54, margin D

Unnumbered paragraph

We are afraid that in the face of the law succinctly laid down in U. P. Cooperative Federation (supra) and reiterated in numerous judgments of this Court referred to earlier, we are unable to accept the wide proposition of law laid down in the foreign judgments cited by Mr. Sorabjee. Whatever may be the law, as to the encashment of bank guarantees in other jurisdictions, when the law in India is clear, settled and without any deviation whatsoever, there 'Id. '(2002) l SLR l. '"Ibid. at pp. 7-8, per LP Thean, JA. is no occasion to rely upon foreign case law. Contentions of the First Respondent

pp. 54–55, margin E

Unnumbered paragraph

A reading of the impugned judgment of the High Court shows that the learned Judge was cognizant of the settled rule relating to bank guarantees, but came to the conclusion that the encashment of the bank guarantees· ~y the Appellant would present a case under one of the exceptions to the rule viz. would cause "irretrievable injustice" to the First Respondent.

p. 55, margin A

Unnumbered paragraph

Learned counsel for the First Responderit strongly supported this line of argument of the High Court. He contended that the bank guarantees were for different purposes, either to: (i) secure the payment of advances or (ii) secure performance. As far as the bank guarantees to secure advance payments were concerned, he contends that there is a provision in the contract that the amount of advance was to be recovered by deduction from the gross accepted amount of any running bill. The contract stipulates two modes of recoveries: (i) By deduction from the gross amount from the running bill, and (ii) By invocation of the bank guarantee. Mr. Sorabjee further urged that it had been found by the District Court and the High Court concurrently that the entire amount of the bank guarantee had been recovered from the running bills of the First Respondent. Accordingly, he argued that, encashing the bank guarantee after having recovered the full amount of advances from the running bills was an "egregious fraud" or at any rate, created a situation of "special equities" in favour of the First Respondent. The High Court, he submits, was fully justified in granting an injunction since these facts were prima facie established as triable issues.

p. 55, margin B

Unnumbered paragraph

Further, Mr. ·sorabjee submitted that the fourth bank guarantee (No. 291199 dated 23 .3 .2000) was further qualified by "due and faithful performance of the contract", and that the contract had been admittedly performed. In the circumstances, he submits that, the encashment of this guarantee was fraudulent or created a situation of special equities, which was covered by U.P. Cooperative Federation Ltd. (supra). Mr. Sorabjee's assertions, however, need closer scrutiny through examining the contractual clauses, as well as through examining the conduct of the First Respondent. The Contractual Clauses

p. 55, margin F

Unnumbered paragraph

Mr. Sorabjee is correct in that both the District Court and the High Court have concurrently held that the documents placed on record do bear out that the entire guarantee amount had been recovered. We are, however, unable to accept Mr. Sorabjee's contention that the bank guarantees given only for the purpose of security as against the advance paid to the Respondent. Indeed, Mr. Rohtagi is justified in his submission that the contract was a "wrap-around agreement". The terms of the agreement on 10.5.2000 make it clear, after referring to the four contract agreements work/ purchase orders, that:

pp. 55–56, margin G

Unnumbered paragraph

" .... .It is specifically agreed between the parties that CONTRACTOR is not only responsible and liable for its scope of supplies in Contract No. I and for its scope of services in the Contract Nos. JI, III but also to perform and take care of all such works which though not specifically mentioned in these four contracts, but are essential complete the "BAGASSE HANDLING SYSTEM PACKAGE" whole in its true intent and requirement unless the exclusion(s) specifically agreed by BSES. Contract-III shall also include unloading of plant and equipment supplied under Contract-I consequent to at site, movement within site to stores and/or to intermediate location and/or to final location, co-ordination with Owner for entry

p. 56, margin B

Unnumbered paragraph

store documents, issue of Store Issue Voucher, etc." The agreement further provides vide Clause (2)

p. 56, margin D

Unnumbered paragraph

"The successful and timely completion of the 'BAGASSE HANDLING SYSTEM PACKAGE' by CONTRACTOR and its performance under Contract-I, Contract-II, Contract-lll and Contract-IV shall jointly and severally bound by the terms of the "Contract" and be jointly and severally liable to BSES for the performance of

p. 56, margin E

Unnumbered paragraph

obligations under the "Contract". Clause (3) of the agreement dee !ares:

p. 56, margin E

Unnumbered paragraph

"CONTRACTOR agrees that if liquidated damages for delay performance guarantees, claim on warranty/workmanship, punch and any breach of contract by CONTRACTOR are applied under provisions of any of the four "Contracts", it automatically shall construed that the same provision can be applied on all the contracts as read together. BSES shall have the right to treat

p. 56, margin F

Unnumbered paragraph

contracts jointly as turnkey contract and money can be recovered Vide (I)

p. 56, margin G

Unnumbered paragraph

BSES including but not limited to liquidated damages, fines or penalties of whatever nature as per the "Contract" and any excess costs and expenses associated with the completion of the job by

p. 57, margin A

Unnumbered paragraph

BSES for the "BAGASSE HANDLING SYSTEM PACKAGE"." Clauses ( 4) and (5) in express tenns respectively ·state:

p. 57, margin A

Unnumbered paragraph

"In case of any material breach of any or all the Contracts, BSES shall have the right to embark upon the retentions and encashment of Bank Guarantees of all the contracts." "Notwithstanding the works undertaken by the designated subcontractor(s) of the Contractor subject to provisions of the contract, the Contractor shall remain wholly liable to perfonn, fulfill and discharge all the obligations and responsibilities under this contract . on a turnkey basis and the same shall in no way be reduced or diminished for any reasons whatsoever."

p. 57, margin B

Unnumbered paragraph

Upon a careful reading of this agreement, we are satisfied that the contract though, for the sake of convenience, was split up into four subcontracts (viz. the four work/ purchase orders), was a composite contract executable on a turnkey basis. The tenns of this turnkey contract were reduced into writing by the "wrap-around agreement" of I0.5.2000. We are of the definite view that under the "wrap-around agreement'', the Appellant had the right to encash any or all of the guarantees for any breach in any of the tenns of the four contracts. Hence, we are unable to accept the submission of Mr. Sorabjee that the first three bank guarantees were only for securing the advances paid and that it was only the fourth bank guarantee (No. 291/99 dated 23 .3 .2000) that was liable to be called for failure to perfonn the contract. In fact, an appraisal of the tenns of the contract leads us to the conclusion that the bank guarantees were intended for both purposes: for securing the advances paid to the First Respondent and also for securing due perfonnance of the contract. Renewal of the Guarantees

p. 57, margin D

Unnumbered paragraph

Our conclusions as to the real purpose of the bank guarantees are fortified by our examination of the conduct of the First Respondent. Indeed, we repeatedly asked Mr. Sorabjee as to why and under what cir~umstances the First Respondent continued the first three guarantees, purportedly pertaining to advances, even after the First Respondent knew that the advance amount had been fully recovered. Mr. Sorabjee claimed sometime to put an Additional Affidavit to deal with this query, which according to him, had been raised by this Court for the first time. In the Additional Affidavit (dated 11.11.2005) filed on behalf of the First Respondent, the explanation given for the continuation of bank guarantees even after full recovery of the advances is that:

pp. 57–58, margin G

Unnumbered paragraph

" ..... the petitioner (the Appellant) has been insisting on extension of bank guarantees and threatened to encash them if they were not extended .... Thus under petitioner's threat of encashment of the bank guarantees, and in the hope of amicably settling the issue with the petitioner, the first respondent (sic) felt compelled to extend the bank guarantees. "

p. 58, margin B

Unnumbered paragraph

In our view, this is an unsatisfactory explanation in the circumstances of the case and in any event, this explanation neither establishes "egregious fraud" by the Appellant nor creates a situation of "irretrievable injury". The Fourth Bank Guarantee

p. 58, margin C

Unnumbered paragraph

Finally, Mr. Sorabjee tried to intervene in the fourth bank guarantee (No.29[/99 dated 23.3.2000) and contended that this was the only bank guarantee intended to secure "due and faithful performance of the contract". He further urged that the performance had been duly satisfied arid, therefore, there was no warrant for calling this bank guarantee. Mr. Sorabjee turned to a certificate issued by M/s Godavari Sugar Mills Ltd. (dated 18.3.2003) to contend that there had been due and satisfactory performance of the contract. We are, however, not impressed with Mr. Sorabjee's argument because the evidence on record is precisely to the contrary. In fact, the certificate, in terms, says that there was a technical defect found:

p. 58, margin D

Unnumbered paragraph

" .... for which correction will be done by Fenner representative (sic) as assured by him. After completion of all those points further tests

p. 58, margin F

Unnumbered paragraph

can be carried out."

p. 58, margin F

Unnumbered paragraph

Accordingly, we are prima facie not satisfied that performance had been duly and satisfactorily certified. Under the terms of the "wrap-around agreement", the Appellant was entitled to encash all or any of the bank guarantees for breach of the First Respondent's obligations under any one of the contracts. In our view, it is the case of the Appellant that ther2 was no "Vide paragraph of the Additional Affidavit filed on behalfofthe First Respondent (dated satisfactory performance of the contract, as a result of which, the Appellant was justified in encashing the concerned bank guarantee. Indeed, as per the · terms of the bank guarantee itself, the Appellant is the best judge to decide as to when and for what reason the bank guarantees should be encashed. Further, it is no function of the Second Respondent-Bank, nor of this Court, to enquire as to whether due performance had actually happened when, under the terms of the guarantee, the Second Respondent-Bank was obliged to make payment when the guarantee was called in, irrespective of any contractual dispute between the Appellant and the First Respondent. Indeed, in similar circumstances, this Court in General Electric Technical Services Company Inc. v. Punj Sons (P) Ltd., held:

pp. 58–59, margin F

Unnumbered paragraph

" ... the Bank must honour the bank guarantee free from interference by the courts. Otherwise, trust in commerce internal and international would be irreparably damaged. It is only in exceptional cases that is to say in case of fraud or in case of irretrievable injustice, the court should interfere. The nature of the fraud that the courts talk about is fraud of an "egregious nature as to vitiate the entire underlying transaction". It is fraud of the beneficiary, not the fraud of somebody

p. 59, margin C

Unnumbered paragraph

else."

p. 59, margin D

Unnumbered paragraph

This was also a case where, after having recovered certain amount from the running bills, a call was made on the bank guarantee in respect of the full guaranteed amount. In an observation with direct relevance for the present case, this Court pointed out that the bank was not concerned with the outstanding amount payable under the running bills:

p. 59, margin D

Unnumbered paragraph

"The right to recover the amount under the running bills has no relevance to the liability of the Bank under the guarantee. The liability . of the Bank·.remained intact irrespective of the recovery of mobilisation advance or the non-payment under the running bills. The failure on the part of.. ... (the Beneficiary)to specify the remaining mobilisation advance in the Jetter for encashment of bank guarantee is of little

p. 59, margin E

Unnumbered paragraph

consequence to the liability Qf the bank under the guarantee." lrre"fi.ie.vable Injury As we have stated repeatedly, the First Respondent can succeed only if

p. 59, margin E

Unnumbered paragraph

sec "Ibid. Jagannatha Shelly, J See also, UP. Cooperative Federation Ltd. Singh Consultants and Engineers Ltd the case can be brought under the two accepted exceptions to the general against intervention. Evidently. there is no ··egregious fraud'' so as to within the first exception. Hence, only one more point remains: whether encashment of the guarantees will create special equities (in particular, "irretrievable injury") in favour of the First Respondent? We are not satisfied on facts that such is the present situation.

pp. 59–60, margin G

Unnumbered paragraph

There is no dispuk that arbitral proceedings are pending. Jn fact, were shown that one of the disputes referred to arbitration is whether bank guarantees are null and void. Further, one of the substantive prayers the arbitration made on behalf of the First Respondent, is to make an award declaring the four bank guarantees unenforceable, illegal, void and liable be discharged. Further, there is also a prayer for permanent injunction restrain the Appellant from encashing the bank guarantees. Therefore, since this prayer is already pending before the Arbitral Tribunal, we see no situation of "irretrievable injustice" if, at the present moment, the Appellant is allowed to encash the bank guarantees. For justice can always be rendered to the First Respondent. if he succeeds before the Arbitrators. Nor do we see any special equity in favour of the First Respondent, when there is in fact a dispute that performance was prima facie not satisfactory, which enabled the Appellant to encash all or any of the four bank guarantees. The Final Findings

p. 60, margin B

Unnumbered paragraph

In this view of the matter, we see no merit in the stand taken by First Respondent. In our judgment, the Madras High Court erred in interfering with the bank guarantees and in granting injunction as sought for. In result, the impugned judgment of the High Court is set aside and the judgment of the learned District Judge, Madurai is affirmed, except with regard to maintenance of status quo directed on the encashment of guarantees. It made clear that the Appellant is entitled to encash the bank guarantees the Second Respondent-Bank shall be free to honour its guarantees, subject to adjustment in the arbitral proceedings.

p. 60, margin E

Unnumbered paragraph

The appeal is accordingly allowed with costs quantified at Rupees Twenty Thousand. B.S. Appeal allowed.

p. 60, margin F